The following items shall be considered when selecting a plant site:
Where a site must be used which is critical with respect to the items in subsection (a), appropriate measures shall be taken to minimize adverse impacts.
The treatment works structures, electrical and mechanical equipment shall be protected from physical damage by the maximum 100 year flood. Treatment works shall remain fully operational during the 25 year flood. This requirement applies to new construction and to existing facilities undergoing major modification. Flood plain regulations of State and Federal agencies shall be considered.
All plant facilities shall be accessible by an all weather road.