Current through Register Vol. 49, No. 2, January 10, 2025
Section 283.220 - Test Plan Requirementsa) A test plan must be submitted to the Agency when an owner or operator of an emission unit intends to average emissions tests results for that unit.b) A test plan must be submitted to the Agency for review prior to conducting any emissions test when any one of the following applies:1) The Agency makes a written request for a test plan;2) A non-standard test method or procedure is to be used;3) A source seeks to test at operating parameters that differ from the maximum parameters specified in its operating permit;4) A source seeks to deviate from a prior test plan for that emission unit; or5) A test plan for the emission unit is required to be submitted by an Illinois Pollution Control Board Order, any court order, consent decree, Compliance Commitment Agreement, or permit provision.c) A test plan must specify:1) The purpose of the test;2) The operating parameters;4) Any other procedures that will be followed when conducting an emissions test pursuant to the provisions of this Part.d) Notwithstanding subsections (a), (b), and (c) above, a test plan need not be submitted under the following circumstances: 1) Where the source intends to utilize a test plan previously submitted to the Agency. However, the source must submit a notice containing the following:A) The purpose of the test;B) Date the previously submitted test plan was submitted to the Agency; andC) A statement that the source is relying on a previously submitted test plan.2) Where the source intends to use a standard test method or procedure. However, the source must submit a notice containing the following:A) The purpose of the test; andB) The standard test method or procedure to be used.e) The Agency is not required to review and approve or disapprove a test plan prior to the owner or operator of an emission unit conducting an emissions test.Ill. Admin. Code tit. 35, § 283.220