Idaho Admin. Code r. 58.01.13.502

Current through September 2, 2024
Section 58.01.13.502 - DECISION TO APPROVE OR DISAPPROVE OF A PERMANENT CLOSURE REPORT
01.Cost Recovery. Final closure of the cyanidation facility will not be approved if any payment required by the cost recovery agreement under Subsection 100.04 is due and unpaid.
02.Issuance of Director's Determination. Within sixty (60) days of receipt of a permanent closure report, the Director will issue to the permittee a Director's determination of approval or disapproval of the permanent closure report. The Director's determination will be based on applicable statutes or rules administered by the Department. The Department will coordinate the evaluation of the permanent closure report with the Idaho Department of Lands.
03.Director's Determination to Disapprove a Permanent Closure Report. A Director's determination to disapprove a permanent closure report will specifically identify and discuss those reasons for disapproval, any administrative actions being considered by the Director, and the permittee's options and procedures for administrative appeal. The Director's determination to disapprove a permanent closure report must include:
a. Identification of errors or inaccuracies in the permanent closure report;
b. Issues or details that require additional clarification;
c. Failures to fully implement the approved permanent closure plans;
d. Outstanding violations or other noncompliance issues; and
e. Other issues supporting the Department's disagreement with the contents, final conclusions or recommendations of the permanent closure report.

Idaho Admin. Code r. 58.01.13.502

Effective March 24, 2022