Current through September 2, 2024
Section 20.03.02.120 - FINANCIAL ASSURANCE REQUIREMENTS01.Submittal of Financial Assurance Before Mining. Prior to beginning any mining on a mine panel covered by a reclamation plan, an operator shall submit to the director, on a Department form, financial assurance meeting the requirements of this rule.02.Submittal of Financial Assurance Before Operating a Cyanidation Facility. Prior to beginning operation of a cyanidation facility an operator will submit to the director, on a Department form, financial assurance meeting the requirements of Section 47-1512(a)(2), Idaho Code. The financial assurance will be in an amount equal to the total costs estimated under paragraph 071.02.k. and Section 120 of these rules.03.Timely Financial Assurance Submittal. Financial assurance must be received by the Department within twenty-four (24) months of reclamation or permanent closure plan approval or the Department will cancel the respective plan without prejudice. If financial assurance is not received within eighteen (18) months of a plan approval, the Department will notify the operator that financial assurance is required prior to the twenty-four (24) month deadline. Extensions will be granted by the director for reasonable cause given if a written request is received prior to the deadline. If financial assurance or an extension request is not received by the deadline, the plan will be canceled. The operator must then submit a new plan application and application fee to restart the approval process.04.Phased Financial Assurance. If the Department approves a reclamation plan or permanent closure plan with phased financial assurance, then financial assurance may increase incrementally commensurate with the additional reclamation or permanent closure liability. After construction and operation of the initial phase has commenced and after filing by an operator of the initial financial assurance, an operator will not construct any component of a subsequent phase or phases of the subject mine or cyanidation facility before filing the additional financial assurance amount that is required by the Board. If phased financial assurance is not authorized, the operator is required to file the financial assurance amount required to complete reclamation or permanent closure of all planned phases prior to any construction of the mine or operation of the cyanidation facility.05.Financial Assurance for Mines with Five (5) or Less Disturbed Acres. Financial assurance will be a minimum of five thousand dollars ($5,000) per acre unless the operator or the Department determine that the estimated reasonable costs of reclamation require a different amount. No financial assurance may exceed fifteen thousand dollars ($15,000) for a given acre of affected land unless the condition in Subsection 120.07 of these rules have been met.06.Financial Assurance for Cyanidation Facility Affecting Five (5) or Less Disturbed Acres. The Board may require financial assurance in excess of five million dollars ($5,000,000) if the conditions in Subsection 120.07 of these rules have been met.07.Process for Requiring Higher Financial Assurance. Financial assurance in excess of the amounts in Subsections 120.05 and 06 of this rule may only be obtained if: a. The Board has determined that such financial assurance is necessary to meet the requirements of the chapter; andb. The Board has delivered to the operator, in writing, a notice setting forth the reasons it believes such financial assurance is necessary; andc. The Board has conducted a hearing where the operator is allowed to give testimony to the Board concerning the amount of the proposed financial assurance, as provided by Section 47-1512, Idaho Code. This requirement for a hearing may be waived, in writing, by the operator.08.Financial Assurance for Mine or Cyanidation Facility with More than Five (5) Disturbed Acres. The amount of financial assurance must be the amount necessary for the Board to pay the estimated reasonable costs of reclamation required under the reclamation plan or permanent closure plan, including indirect costs in Section 120 of these rules.09.Mobilization Costs are Direct Costs. Mobilization and demobilization costs will be included in financial assurance calculations as a direct cost. Costs will be calculated to the mine from the nearest community that has at least two (2) contractors able to perform the reclamation.10.Indirect Costs for Reclamation Cost Calculations. Reclamation and permanent closure cost calculations shall include the following indirect costs and should fall within the percentages given. If a different percentage is used, then a justification must be given. Alternatively, an operator may propose the use of an industry recognized standardized reclamation cost estimation tool for use in reclamation and/or permanent closure cost estimates and the use of the tool's associated indirect costs which are established using the project direct costs as identified:a. Contractor profit at six percent to ten percent (6% to 10%) of direct costs;b. Contractor overhead at four percent to eight percent (4% to 8%) of direct costs;c. Contractor insurance at one and a half percent (1.5%) of labor costs;d. Contractor bonding at two and a half percent to three and a half percent (2.5% to 3.5%) of direct costs;e. Contract administration at five percent to nine percent (5% to 9%) of direct costs;f. Re-engineering for mines or cyanidation facilities with direct reclamation costs over five hundred thousand dollars ($500,000). Re-engineering will be three percent to seven percent (3% to 7%) of direct costs;g. Scope contingency at six percent to eleven percent (6% to 11%) of direct costs;h. Bid contingency at six percent to eleven percent (6% to 11%) of direct costs; andi. Other site specific costs as appropriate.11.Salvage Value Not Allowed. Reclamation or permanent closure costs will not be reduced by assigning a salvage value to structures or fixtures to be removed during reclamation.12.Mining Operation Conducted by Public or Government. Notwithstanding any other provision of law to the contrary, the financial assurance provisions of the chapter and these rules do not apply to any surface mining operations conducted by a public or governmental agency for maintenance, repair, or construction of a public highway.13.Annual Financial Assurance Review for Reclamation Plans. At the beginning of each calendar year, the operator shall notify the director of any increase in the acreage of affected land beyond that covered by the existing financial assurance which will result from planned mining activity within the next twelve (12) months. A commensurate increase in the financial assurance will be required for an increase in affected acreage. Any additional financial assurance required must be submitted on the appropriate form within ninety (90) days of operator's receipt of notice from the Department that an additional amount is required. In no event will mining operations be conducted that would affect additional acreage until the appropriate form and financial assurance has been submitted to the Department. Acreage on which reclamation is complete will be reported in accordance with Subsection 120.16 of these rules and after release of this acreage from the reclamation plan by the director, the financial assurance will be reduced by the amount appropriate to reflect the completed reclamation.14.Financial Assurance Provided to the Federal Government. Any financial assurance provided to the federal government that also meets the requirements of Section 120 of these rules will be sufficient for the purposes of these rules. A mine providing financial assurance through an order under the Comprehensive Environmental Response, Compensation, and Liability Act is not required to submit financial assurance to the Department as described in Idaho Code 47-1512(n).15.Financial Assurance Reduction for Mines.a. An operator may petition the director for a change in the initial financial assurance amount. The director will review the petition and if satisfied with the information presented a revised financial assurance amount will be determined. The revised amount will be based upon the estimated cost that the director would incur should a forfeiture of financial assurance occur and it became necessary for the director, through contracting with a third party, to complete reclamation to the standards established in the plan.b. Upon finding that any land covered by financial assurance will not be affected by mining, the operator will notify the director. The amount of the financial assurance will be reduced by the amount being held to reclaim those lands.c. Any request for financial assurance reduction will be answered by the director within thirty (30) days of receiving such request unless weather conditions prevent inspection.16.Financial Assurance Release Following Mine Reclamation. Upon completion of all or a portion of the reclamation or post-closure activity specified in the plan, the operator may notify the director of his desire to secure release from financial assurance. When the director has verified that the requirements of the reclamation plan have been substantially met as stated in the plan, the financial assurance will be released.a. Any request for financial assurance release will be answered by the director within thirty (30) days of receiving such request unless weather conditions prevent inspection.b. If the director finds that a specific portion of the reclamation or post-closure has been substantially completed, the financial assurance may be reduced to the amount required to complete the remaining reclamation or post-closure. The following schedule will be used to complete these financial assurance reductions unless the director determines in a specific case that this schedule is not appropriate and specifies a different schedule, or the approved reclamation plan has a different schedule based on site-specific conditions.i. Sixty percent (60%) of the financial assurance may be released when the operator completes the required backfilling, regrading, topsoil replacement, and drainage control of a specific area in accordance with the approved reclamation plan; andii. After revegetation activities have been performed by the operator on the regraded lands, according to the approved reclamation plan, the Department may release an additional twenty-five percent (25%) of the financial assurance.c. The remaining financial assurance shall not be released:i. As long as the affected lands are contributing suspended solids to surface waters outside the affected area in excess of state water quality standards and in greater quantities than existed prior to the commencement of mining operations;ii. Until final removal of equipment and structures related to the mining activity or until any remaining equipment and structures are brought under an approved reclamation plan and financial assurance by a new operator; andiii. Until all temporary sediment or erosion control structures have been removed and reclaimed or until such structures are brought under an approved reclamation plan and financial assurance by a new operator.17.Corporate Guarantee Released First. If an operator provides part of their financial assurance through a corporate guarantee, then the corporate guarantee will be released prior to any other type of financial assurance being released. Other types of financial assurance will only be released after the corporate guarantee has been completely released.18.Cooperative Agreements. The director may through private conference, conciliation, and persuasion reach a cooperative agreement with the operator to correct deficiencies in complying with the reclamation plan and thereby postpone action to forfeit the financial assurance and cancel the reclamation plan if all deficiencies are satisfactorily corrected within the time specified by the cooperative agreement.19.Permanent Closure Financial Assurance Review. The Department will periodically review all financial assurances filed for permanent closure to determine their sufficiency to complete the work required by an approved permanent closure plan. For reviews conducted under paragraphs a and b the director may employ a qualified independent party to verify the accuracy of the revised permanent closure cost estimate as described in paragraph 071.05.b. of these rules. a. Once every three (3) years, the operator must submit an updated permanent closure cost estimate to the Department for review. The director will review the updated estimate to determine whether the existing financial assurance amount is adequate to implement the permanent closure plan, as approved by the Department. Any resulting change in the financial assurance amount does not in and of itself require an amendment to the permanent closure plan as may be required by Section 091 of these rules. The director will review the estimate to determine whether the existing financial assurance amount is adequate to complete permanent closure of the cyanidation facility.b. When the director determines that there has been a material change in the estimated reasonable costs to complete permanent closure: i. The director will notify the operator in writing of his intent to reevaluate the financial assurance amount. Within a reasonable time period determined by the Department, the operator will provide to the Department a revised cost estimate to complete permanent closure as approved by the Department.ii. Within thirty (30) days of receipt of the revised cost estimate, the director will notify the operator in writing of his determination of financial assurance adequacy.iii. Within ninety (90) days of notification of the director's assessment, the operator will make the appropriate adjustment to the financial assurance or the director will reduce the financial assurance as appropriate.c. The Department may conduct an internal review of the amount of each financial assurance annually to determine whether it is adequate to complete permanent closure.20.Permanent Closure Financial Assurance Release.a. A financial assurance filed for permanent closure of a cyanidation facility will be released according to the schedule in the permanent closure plan. The schedule will include provisions for the release of the post-closure monitoring and maintenance portions of the financial assurance. The schedule may be adjusted to reflect the operator's performance of permanent closure activities and their demonstrated effectiveness.b. Upon completion of an activity required by an approved permanent closure plan, the operator may request in writing a financial assurance reduction for that activity. The Department will notify the operator within thirty (30) days whether or not the activity meets the requirements of the permanent closure plan. When the director, in consultation with DEQ, has verified that the activity meets the requirements of the permanent closure plan, the financial assurance will be reduced by an amount to reflect the activity completed.c. Upon the director's determination that all activities specified in the permanent closure plan have been successfully completed, the Department will, in accordance with Section 47-1512(i), Idaho Code, release the balance remaining after partial financial assurance releases.21.Liabilities for Reclamation Costs Not Covered by Financial Assurance. An operator who is not required to furnish financial assurance by these rules but fails to reclaim may be subject to civil penalty under Section 47-1513(c), Idaho Code. The amount of civil penalty will be the estimated cost of reasonable reclamation of affected lands as determined by the director. Reasonable reclamation of the site will be presumed to be in accordance with the standards established in the approved reclamation plan. The amount of the civil penalty is in addition to those described in Section 47-1513(f), Idaho Code.22.Appeal Process for Financial Assurance Decisions. All decisions regarding financial assurance extension requests, plan cancellation, financial assurance reduction, or financial assurance release as described in Section 120 of these rules are subject to appeal as described in Section 58-104, Idaho Code, and Section 47-1514, Idaho Code.Idaho Admin. Code r. 20.03.02.120