Haw. Code R. § 19-170-198

Current through November, 2024
Section 19-170-198 - Certification
(a) Upon completion of improvements, and prior to approval, the improvements shall be inspected by the executive officer, upon consultation with the chief engineer, traffic engineer, director of the city's department of parks and recreation, wastewater management director and manager. The cost of testing any improvement, if required by the executive officer, shall be borne by the subdivider.
(b) If the street lighting conforms to approved plans and specifications, and the installation is energized and continues in proper operating condition for a period of one week, the development corporation shall approve the installation and issue a certificate to the subdivider attesting to such inspection, test, and approval. The subdivider shall arrange with the public power company and bear the cost of arrangements and electrical energy used for the tests.
(c) Subdivision improvements shall not be approved by the executive officer until the subdivider has received written certification that they are complete and acceptable to the development corporation. The subdivider must accomplish the following, in addition to the testing above, in order to obtain such certification:
(1) File tracings of construction plans as actually constructed, showing all changes from the original plans, with the executive officer and the department of wastewater management.
(2) File duplicate tracings of the sewer system as actually constructed showing all changes from the original plans with the executive officer and the department of wastewater management.
(3) File tracings of the street lighting system and traffic control devices as actually constructed, showing all changes from the original plans, with the executive officer and the department of transportation services.
(4) File tracings of the street tree planting plans as planted, with the executive officer and the department of recreation.
(5) File tracings of the water system as actually constructed, showing all changes from the original plans, with the executive officer and the board of water supply.

Haw. Code R. § 19-170-198

[Eff MAY 5 2013] (Auth: HRS §§ 206J-5(5), 206J-7) (Imp: HRS § 206J-7)