Section 15-307-245 - Processing of regional infrastructure project proposals
(a) An applicant shall make a written request including and supported by information, materials, forms and exhibits about the project as set forth in §15-307-26, above, as applicable to the project, and such additional information as may be required by the corporation.
(b) The administrator shall, upon receipt of an application or project proposal or both, time stamp the same as received and review the application for completeness and compliance with applicable rules under this subchapter. An incomplete application shall be returned to the applicant.
(c) After review of the application for appropriateness, technical compliance and feasibility, the administrator may submit the proposal with a recommendation for approval, contingent approval, or disapproval to the board.
(d) The board may recommend that a request for regional infrastructure subaccount funds be allocated or may deny a request for regional infrastructure subaccount funds for a project. The board may also defer action on any request for regional infrastructure subaccount funds and may request that additional information be submitted. If the board recommends that a request for regional infrastructure subaccount funds be allocated for a project, the board shall make specific findings that the use and application of regional infrastructure subaccount funds for the project are consistent with the purposes of this subchapter.

Haw. Code R. § 15-307-245

[Eff 4/28/2017] (Auth: HRS § 201H-4, Act 132, SLH 2016) (Imp: Act 132, SLH 2016)
[Comp 1/15/2022] (Auth: HRS §§ 201H-191.5) (Imp: § 201H-191.5)