Section 15-219-100 - Time period for compliance
(a) When determining the corrective action to be taken and a reasonable deadline to correct the violation, the executive director shall use the following schedule as a guide:

Schedule for Correction of Violations

Type of Violation Initial Violation Repeated Violation
Land Use 15 days 7 days or less
Development Standard 30 days 15 days or less
Permit Condition 30 days 15 days or less

(b) This schedule is only a guide and may be modified in consideration of the following:
(1) The type and the degree of the violation, whether it is a repeated violation, and the number of violations cited in the citation;
(2) Whether the violation poses a threat or potential threat to human health and safety;
(3) Procedural requirements for obtaining a permit or authorization to carry out corrective action;
(4) The complexity of the corrective action required, including construction requirements and the legal prerogatives of landlords and tenants; and
(5) Any other circumstances beyond the control of the violator.