Haw. Code R. § 15-217-86

Current through November, 2024
Section 15-217-86 - Automatic approvals
(a) The following permits shall be deemed approved and require no public hearing if a certificate of completeness has been issued and no decision is rendered within the following review periods:
(1) Rules clearance (sixty calendar days);
(2) Improvement Permit (ninety calendar days);
(3) Development permit (one hundred eighty calendar days);
(4) Conditional use of vacant land permit (ninety days);
(5) Conditional use permit (one hundred eighty calendar days);
(6) Variance (one hundred eighty calendar days); and
(7) Master plan (two hundred calendar days).
(b) Whenever a proposed project requires more than one permit, the longest review period of section 15-22-86(a) shall apply for determining the deemed approved date.

Haw. Code R. § 15-217-86

[Eff NOV 11 2011 ] (Auth: HRS §§ 206E-4, 206E-5, 206E-7) (Imp: HRS §§ 206E-4, 206E-5, 206E-7)