The following fee schedule shall be applicable to all permits, rule clearance, and public hearings.
Rule Clearance | $20.00 |
Improvement Permit | Cost: Project Size: $20 up to 1,000 s.f. $100 1,001-10,000 s.f. $500 10,001-30,000 s.f. $1,000 > 30,000 s.f. |
Development Permit | $6,400 plus the cost of public hearing |
Master Plan Permit | $10,000 plus the cost of public hearing |
Variance | $500 plus the cost of public hearing |
Haw. Code R. § 15-215-91