Haw. Code R. § 15-215-84

Current through November, 2024
Section 15-215-84 - Automatic approvals

The following permits shall be deemed approved if a certificate of completeness has been issued and no decision is rendered within the following review periods:

(1) Rules clearance and conditional use of vacant land (sixty calendar days);
(2) Improvement Permit (ninety calendar days);
(3) Development permit (one hundred twenty calendar days);
(4) Conditional use permit (one hundred twenty calendar days);
(5) Variance (one hundred sixty calendar days); and
(6) Master plan (two hundred calendar days).

Haw. Code R. § 15-215-84

[Eff OCT 27 2012] (Auth: HRS §§ 206E-4, 206E-5, 206E-7) (Imp: HRS §§ 206E-4, 206E-5, 206E-7)