Haw. Code R. § 15-16-93

Current through November, 2024
Section 15-16-93 - Time period for compliance
(a) When determining the corrective action to be taken and a reasonable deadline to correct the violation, the executive director shall use the following schedule as a guide:

Schedule for Correction of Violations

Type of ViolationInitial ViolationRepeated Violation
Use15 days 7 days or less
Development Standard30 days15 days or less
Permit Condition30 days15 days or less

(b) This schedule is only a guide and may be modified in consideration of the following:
(1) The type and the degree of the violation, whether it is a repeated violation, and the number of violations cited in the citation;
(2) Whether the violation poses a threat or potential threat to human health and safety;
(3) The intent of the violator to comply, if it has been expressed to the executive director;
(4) Procedural requirements for obtaining a permit or authorization to carry out corrective action;
(5) The complexity of the corrective action required, including construction requirements and the legal prerogatives of landlords and tenants; and
(6) Any other circumstances beyond the control of the violator.

Haw. Code R. § 15-16-93

[Eff 10/3/94] (Auth: HRS §§ 91-2, 206E-4, 206E-22) (Imp: HRS §§ 206E-5, 206E-7, 206E-22)