Section 15-32-6 - Application procedure

Any business applying for a grant shall, as applicable, either:

(1) Upon receipt of notification by the awarding federal agency that an SBIR or STTR phase I, phase II, or phase III award has been approved and funded, forward a copy of the accepted proposal and a copy of the notification of award to the chief executive officer of the development corporation as part of the application; or
(2) Forward a copy of its application for an SBIR or STTR federal award and a copy of the federal agency's acknowledgment of receipt of a completed application to the chief executive officer of the development corporation as part of the application.

Haw. Code R. § 15-32-6

[Eff. DEC 21 1989] (Auth: HRS secs. 91-2, 206M-15) (Imp: HRS secs. 91-2, 206M-15)
Am and comp 12/13/12; am and comp 3/11/2016