Haw. Code R. § 11-200.1-24

Current through September, 2024
Section 11-200.1-24 - Content requirements; draft environmental impact statement
(a) The draft EIS, at a minimum, shall contain the information required in this section. The contents shall fully declare the environmental implications of the proposed action and shall discuss all reasonably foreseeable consequences of the action. In order that the public can be fully informed and that the accepting authority can make a sound decision based upon the full range of responsible opinion on environmental effects, an EIS shall include responsible opposing views, if any, on significant environmental issues raised by the proposal.
(b) The scope of the draft EIS may vary with the scope of the proposed action and its impact, taking into consideration whether the action is a project or a program. Data and analyses in a draft EIS shall be commensurate with the importance of the impact, and less important material may be summarized, consolidated, or simply referenced. A draft EIS shall indicate at appropriate points in the text any underlying studies, reports, and other information obtained and considered in preparing the draft EIS, including cost-benefit analyses and reports required under other legal authorities.
(c) The level of detail in a draft EIS may be more broad for programs or components of a program for which site-specific impacts are not discernible, and shall be more specific for components of the program for which site-specific, project-level impacts are discernible. A draft EIS for a program may, where necessary, omit evaluating issues that are not yet ready for decision at the project level. Analysis of the program may discuss in general terms the constraints and sequences of events likely to result in any narrowing of future options. It may present and analyze in general terms hypothetical scenarios that are likely to occur.
(d) The draft EIS shall contain a summary that concisely discusses the following:
(1) Brief description of the action;
(2) Significant beneficial and adverse impacts,*
(3) Proposed mitigation measures;
(4) Alternatives considered*
(5) Unresolved issues;
(6) Compatibility with land use plans and policies, and a list of permits or approvals; and
(7) A list of relevant EAs and EISs considered in the analysis of the preparation of the EIS.
(e) The draft EIS shall contain a table of contents.
(f) The draft EIS shall contain a separate and distinct section that includes the purpose and need for the proposed action.
(g) The draft EIS shall contain a description of the action that shall include the following information, but need not supply extensive detail beyond that needed for evaluation and review of the environmental impact:
(1) A detailed map (such as a United States Geological Survey topographic map, Flood Insurance Rate Maps, Floodway Boundary Maps, or state sea level rise exposure area maps, as applicable) and a related regional map;
(2) Objectives of the proposed action;
(3) General description of the action's technical, economic, social, cultural, and environmental characteristics;
(4) Use of state or county funds or lands for the action;
(5) Phasing and timing of the action;
(6) Summary technical data, diagrams, and other information necessary to enable an evaluation of potential environmental impact by commenting agencies and the public; and
(7) Historic perspective.
(h) The draft EIS shall describe in a separate and distinct section discussion of the alternative of no action as well as reasonable alternatives that could attain the objectives of the action. The section shall include a rigorous exploration and objective evaluation of the environmental impacts of all such alternative actions. Particular attention shall be given to alternatives that might enhance environmental quality or avoid, reduce, or minimize some or all of the adverse environmental effects, costs, and risks of the action. Examples of alternatives include:
(1) Alternatives requiring actions of a significantly different nature that would provide similar benefits with different environmental impacts;
(2) Alternatives related to different designs or details of the proposed action that would present different environmental impacts; and
(3) Alternative locations for the proposed action. In each case, the analysis shall be sufficiently detailed to allow the comparative evaluation of the environmental benefits, costs, and risks of the proposed action and each reasonable alternative. For alternatives that were eliminated from detailed study, the section shall contain a brief discussion of the reasons for not studying those alternatives in detail. For any agency actions, the discussion of alternatives shall include, where relevant, those alternatives not within the existing authority of the agency.
(i) The draft EIS shall include a description of the environmental setting, including a description of the environment in the vicinity of the action, as it exists before commencement of the action, from both a local and regional perspective. Special emphasis shall be placed on environmental resources that are rare or unique to the region and the action site (including natural or human-made resources of historic, cultural, archaeological, or aesthetic significance); specific reference to related actions, public and private, existent or planned in the region shall also be included for purposes of examining the possible overall cumulative impacts of such actions. Proposing agencies and applicants shall also identify, where appropriate, population and growth characteristics of the affected area, any population and growth assumptions used to justify the proposed action, and any secondary population and growth impacts resulting from the proposed action and its alternatives. The draft EIS shall expressly note the sources of data used to identify, qualify, or evaluate any and all environmental consequences.
(j) The draft EIS shall include a description of the relationship of the proposed action to land use and natural or cultural resource plans, policies, and controls for the affected area. Discussion of how the proposed action may conform or conflict with objectives and specific terms of approved or proposed land use and resource plans, policies, and controls, if any, for the affected area shall be included* Where a conflict or inconsistency exists, the draft EIS shall describe the extent to which the agency or applicant has reconciled its proposed action with the plan, policy, or control, and the reasons why the agency or applicant has decided to proceed, notwithstanding the absence of full reconciliation*
(k) The draft EIS shall also contain a list of necessary approvals required for the action from governmental agencies, boards, or commissions or other similar groups having jurisdiction. The status of each identified approval shall also be described.
(l) The draft EIS shall include an analysis of the probable impact of the proposed action on the environment, and impacts of the natural or human environment on the action. This analysis shall include consideration of all phases of the action and consideration of all consequences on the environment, including direct and indirect effects. The interrelationships and cumulative environmental impacts of the proposed action and other related actions shall be discussed in the draft EIS. The draft EIS should recognize that several actions, in particular those that involve the construction of public facilities or structures (e.g., highways, airports, sewer systems, water resource actions, etc.) may well stimulate or induce secondary effects. These secondary effects may be equally important as, or more important than, primary effects, and shall be thoroughly discussed to fully describe the probable impact of the proposed action on the environment. The population and growth impacts of an action shall be estimated if expected to be significant, and an evaluation shall be made of the effects of any possible change in population patterns or growth upon the resource base, including but not limited to land use, water, and public services, of the area in question. Also, if the proposed action constitutes a direct or indirect source of pollution as determined by any governmental agency, necessary data regarding these impacts shall be incorporated into the EIS. The significance of the impacts shall be discussed in terms of subsections (m), (n), (o), and (p).
(m) The draft EIS shall include in a separate and distinct section a description of the relationship between local short-term uses of humanity's environment and the maintenance and enhancement of long-term productivity. The extent to which the proposed action involves trade-offs among short-term and long-term gains and losses shall be discussed. The discussion shall include the extent to which the proposed action forecloses future options, narrows the range of beneficial uses of the environment, or poses long-term risks to health or safety. In this context, short-term and long-term do not necessarily refer to any fixed time periods, but shall be viewed in terms of the environmentally significant consequences of the proposed action.
(n) The draft EIS shall include in a separate and distinct section a description of all irreversible and irretrievable commitments of resources that would be involved in the proposed action should it be implemented. Identification of unavoidable impacts and the extent to which the action makes use of non-renewable resources during the phases of the action, or irreversibly curtails the range of potential uses of the environment, shall also be included. The possibility of environmental accidents resulting from any phase of the action shall also be considered.
(o) The draft EIS shall address all probable adverse environmental effects that cannot be avoided. Any adverse effects such as water or air pollution, urban congestion, threats to public health, or other consequences adverse to environmental goals and guidelines established by environmental response laws, coastal zone management laws, pollution control and abatement laws, and environmental policy including those found in chapters 128D (Environmental Response Law), 205A (Coastal Zone Management), 342B (Air Pollution Control), 342C (Ozone Layer Protection), 342D (Water Pollution), 342E (Nonpoint Source Pollution Management and Control), 342F (Noise Pollution), 342G (Integrated Solid Waste Management), 342H (Solid Waste Recycling), 3421 (Special Wastes Recycling), 342J (Hazardous Waste, including Used Oil), 342L (Underground Storage Tanks), 342P (Asbestos and Lead), and 344 (State Environmental Policy), HRS, and those effects discussed in this section that are adverse and unavoidable under the proposed action must be addressed in the draft EIS. Also, the rationale for proceeding with a proposed action, notwithstanding unavoidable effects, shall be clearly set forth in this section. The draft EIS shall indicate what other interests and considerations of governmental policies are thought to offset the adverse environmental effects of the proposed action. The draft EIS shall also indicate the extent to which these stated countervailing benefits could be realized by following reasonable alternatives to the proposed action that would avoid some or all of the adverse environmental effects.
(p) The draft EIS shall consider mitigation measures proposed to avoid, minimize, rectify, or reduce impacts, including provision for compensation for losses of cultural, community, historical, archaeological, and fish and wildlife resources, including the acquisition of land, waters, and interests therein. Description of any mitigation measures included in the action plan to reduce significant, unavoidable, adverse impacts to insignificant levels, and the basis for considering these levels acceptable shall be included. Where a particular mitigation measure has been chosen from among several alternatives, the measures shall be discussed and reasons given for the choice made. The draft EIS shall include, where possible, specific reference to the timing of each step proposed to be taken in any mitigation process, what performance bonds, if any, may be posted, and what other provisions are proposed to ensure that the mitigation measures will in fact be taken in the event the action is implemented.
(q) The draft EIS shall include a separate and distinct section that summarizes unresolved issues and contains either a discussion of how such issues will be resolved prior to commencement of the action, or what overriding reasons there are for proceeding without resolving the issues.
(r) The draft EIS shall include a separate and distinct section that contains a list identifying all governmental agencies, other organizations and private individuals consulted in preparing the draft EIS, and shall disclose the identity of the persons, firms, or agency preparing the draft EIS, by contract or other authorization.
(s) The draft EIS shall include a separate and distinct section that contains:
(1) Reproductions of all written comments submitted during the consultation period required in section 11-200.1-23;
(2) Responses to all substantive written comments made during the consultation period required in section 11-200.1-23. Proposing agencies and applicants shall respond in the draft EIS to all substantive written comments in one of two ways, or a combination of both, so long as each substantive comment has clearly received a response:
(A) By grouping comment responses under topic headings and addressing each substantive comment raised by an individual commenter under that topic heading by issue. When grouping comments by topic and issue, the names of commenters who raised an issue under a topic heading shall be clearly identified in a distinctly labeled section with that topic heading. All substantive comments within a single comment letter must be addressed, but may be addressed throughout the applicable different topic areas with the commenter identified in each applicable topic area. All comments, except those described in paragraph (3), must be appended in full to the final document; or
(B) By providing a separate and distinct response to each comment clearly identifying the commenter and the comment receiving a response being responded to for each comment letter submitted. All comments, except those described in paragraph (3), must either be included with the response, or appended in full to the final document;
(3) For comments that are form letters or petitions, that contain identical or near-identical language, and that raise the same issues on the same topic:
(A) The response may be grouped under paragraph(2)(A) with the response to other comments under the same topic and issue with all commenters identified in the distinctly labeled section identifying commenters by topic; or
(B) A single response may be provided that addresses all substantive comments within the form letter or petition and that includes a distinct section listing the individual commenters who submitted the form letter or petition. At least one representative sample of the form letter or petition shall be appended to the final document; and
(C) Provided that, if a commenter adds a distinct substantive comment to a form letter or petition, then that comment must be responded to pursuant to paragraph (2);
(4) A summary of any EIS public scoping meetings, including a written general summary of the oral comments made, and a representative sample of any handout provided by the proposing agency or applicant related to the action provided at any EIS public scoping meeting;
(5) A list of those persons or agencies who were consulted and had no comment in a manner indicating that no comment was provided; and
(6) A representative sample of the consultation request letter.
(t) An addendum to a draft EIS shall reference the original draft EIS to which it attaches and comply with all applicable filing, public review, and comment requirements set forth in subchapter 10.

Haw. Code R. § 11-200.1-24

[Eff AUG 9 2019] (Auth: HRS §§ 343-5, 343-6) (Imp: HRS §§ 343-2, 343-5, 343-6)