Ga. Comp. R. & Regs. 351-4-.01

Current through Rules and Regulations filed through November 21, 2024
Rule 351-4-.01 - Production Pre-operational Inspections
(1) A production licensee shall submit to pre-operational progress inspections conducted by the Commission or its employees to ensure and confirm that the production licensee is fully operational as required by Code Section 16-12-223(a)(5).
(2) Prior to the inspection to be deemed fully operational, a production licensee shall submit the following to the Commission:
(a) A satisfactory report of full compliance with, and completion of, all applicable public safety inspections required by local, state, and federal jurisdictions, including, without limitation, fire, building, health, and air quality inspections; and
(b) A list of all plant strains and cultivars which will be propagated and/or cultivated at the premises, which shall be maintained at the premises during the term of the production license contract and provided to the Commission or its employees upon request.
(3) Failure of a production licensee to be fully operational within twelve (12) months of the date the license is awarded will result in the revocation of the license and any associated dispensing licenses.

Ga. Comp. R. & Regs. R. 351-4-.01

O.C.G.A. §§ 16-12-203, 16-12-206, 16-12-210, 16-12-211, 16-12-212, 16-12-217, 16-12-223.

Original Rule entitled "Production Pre-operational Inspections" adopted. F. Mar. 16, 2023; eff. Apr. 5, 2023.