a. Construction permit for an emissions unit having potential emissions of 100 or more tons per year of any single pollutant. | $5,000.00 |
b. Construction permit for an emissions unit having potential emissions of 50 or more tons per year, but less than 100 tons per year, of any single pollutant. | $4,500.00 |
c. Construction permit for an emissions unit having potential emissions of 25 or more tons per year, but less than 50 tons per year, of any single pollutant. | $2,000.00 |
d. Construction permit for an emissions unit having potential emissions of 5 or more tons per year, but less than 25 tons per year, of any single pollutant. | $1,000.00 |
e. Construction permit for an emissions unit having potential emissions of less than 5 tons per year of each pollutant. | $250.00 |
3. Operation Permit Fee for an Emissions Unit at a Non-Title V Source. | |
a. Operation permit for an emissions unit required to measure actual emissions by stack sampling. | $1,500.00 |
b. Operation permit for an emissions unit required to measure actual emissions by any method other than stack sampling (such as visible emissions observation or continuous emissions monitoring). | $1,000.00 |
c. Operation permit for an emissions unit not required to measure actual emissions. | $750.00 |
Type II | Type III | ||
a. Treatment plant with or without reuse/disposal system. | $5,000.00 | $3,750.00 | $1,200.00 |
b. Reuse/land application system and associated transmission/distribution facilities, when applied for separately from the treatment facility. | $5,000.00 | $3,750.00 | $1,200.00 |
c. Residuals/septage management facility. | $7,500.00 | $4,000.00 | $1,200.00 |
d. Limited wet weather discharge. | $1,000.00 | $800.00 | $600.00 |
Type I | Type II | Type III | |
a. Treatment plant with or without reuse/disposal system. | $5,000.00 | $3,000.00 | $1,000.00 |
b. Reuse/land application system and associated transmission/distribution facilities, when applied for separately from the treatment facility. | $5,000.00 | $3,000.00 | $1,000.00 |
c. Residuals/septage management facility. | $7,500.00 | $4,000.00 | $1,000.00 |
d. Limited wet weather discharge. | $1,000.00 | $800.00 | $600.00 |
e. Wastewater permits for Type III facilities having a permitted capacity of less than 10, 000 gallons per day shall be $600. |
a. Type I facility. | $2,000.00 |
b. Type II facility. | $1000.00 |
c. Type III facility. | $500.00 |
a. Type I facility. | $500.00 |
b. Type II facility. | $300.00 |
c. Type III facility. | $100.00 |
a. Treatment facility with permitted capacity of 10,000 gallons per day up to 100,000 gallons per day shall be: | $1,000.00 |
b. Treatment facility with permitted capacity less than 10,000 gallons per day shall be: | $600.00 |
a. Domestic wastewater collection/transmission system serving 10 or more. | $500.00 |
Equivalent Dwelling Units (EDUs). An EDU is equal to 3.5 persons. | |
b. Domestic wastewater collection/transmission system serving less than 10 EDUs. | $300.00 |
a. Surface water discharges. | $7,500.00 |
b. Non-surface water discharges only. | $6,000.00 |
a. Surface water discharges. | $5,000.00 |
b. Non-surface water discharges only. | $4,000.00 |
a. Surface water discharges. | $2,500.00 |
b. Non-surface water discharges only. | $2,000.00 |
a. Feedlots with greater than the number of animals listed in subsection 62-670.200(3), or Rule 62-620.435, F.A.C. | $2,500.00 |
b. Feedlots, Other | $1,500.00 |
c. Egg Production Facility, Major. | $2,500.00 |
d. Egg Production Facility, Other. | $1,500.00 |
a. Design daily discharge flow of greater than 500,000 gpd. | $6,000.00 |
b. Design daily discharge flow of greater than 100,000 gpd up to 500,000 gpd. | $4,000.00 |
c. Design daily discharge flow of greater than 10,000 gpd up to 100,000 gpd. | $2,000.00 |
d. Design daily discharge flow of 10,000 gpd or less. | $750.00 |
a. Greater than 100 million BTU/hour heat loss. | $6,000.00 |
b. Greater than 20 million BTU/hour, up to 100 million BTU/hour. | $3,000.00 |
c. Greater than 1 million BTU/hour, up to 20 million BTU/hour heat loss. | $1,500.00 |
d. 1 million BTU/hour, or less, heat loss. | $500.00 |
a. Design daily flow of greater than 500,000 gpd. | $5,000.00 |
b. Design daily flow of greater than 100,000 gpd up to 500,000 gpd. | $3,000.00 |
c. Design daily flow of greater than 50,000 gpd up to 100,000 gpd. | $2,000.00 |
d. Design daily flow of 50,000 gpd or less. | $1,000.00 |
a. Design daily flow of greater than 500,000 gpd. | $4,000.00 |
b. Design daily flow of greater than 100,000 gpd up to 500,000 gpd. | $2,500.00 |
c. Design daily flow of greater than 50,000 gpd up to 100,000 gpd. | $1,500.00 |
d. Design daily flow of 50,000 gpd or less. | $750.00 |
a. Facilities recycling greater than 10,000 gpd. | $500.00 |
b. Facilities recycling 10,000 gpd or less. | $100.00 |
a. Facilities which have no discharge to surface or ground waters. | $100.00 |
b. All others. | $250.00 |
a. General and generic permits requiring Professional Engineer or Professional Geologist certification. | $500.00 |
b. General and generic permits not requiring Professional Engineer or Professional Geologist certification. | $100.00 |
14. Collection systems for industrial wastewater treatment facilities. | $500.00 |
15. A permitted facility which falls in more than one of the fee categories in subparagraphs (4)(c)1. through 8., shall not be subject to multiple fees, but shall pay the larger of the fees. |
1. Generic Permit for Stormwater Discharge from Large and Small Construction Activities. | |
a. Activities disturbing 5 or more acres (large). | $400.00 |
b. Activities disturbing 1 acre of land or greater and less than 5 acres (small). | $250.00 |
2. Multi-Sector Generic Permit for Stormwater Discharge Associated with Industrial Activity. | $500.00 |
3. No Exposure Certification for Exclusion from NPDES Stormwater Permitting. | $200.00 |
4. Stormwater discharge associated with industrial activity permitted under Chapter 62-620, F.A.C. | $1,000.00 |
5. Generic Permit for Discharge of Stormwater from Phase II Municipal Separate Storm Sewer Systems (MS4s): | |
a. Phase II MS4s in jurisdiction with a population of 50,000 or greater as determined by the 2000 Decennial Census by the U.S. Bureau of Census. | $11,700.00 |
b. Phase II MS4s in a jurisdiction with a population of greater than 10,000 but less than 50,000 as determined by the 2000 Decennial Census by the U.S. Bureau of Census. | $7,988.00 |
c. Phase II MS4s in a jurisdiction with a population of 10,000 or less as determined by the 2,000 Decennial Census by the U.S. Bureau of Census; Florida Department of Transportation facilities. | $5,625.00 |
a. Standard form projects including dredge and fill activities that affect 10 or more acres of jurisdictional area pursuant to subsection 62-312.070(2), F.A.C. | $4,000.00 |
b. Standard form construction projects that involve the construction of new docking facilities pursuant to Rule 62-312.070, F.A.C., that provide: | |
(I) 50 or more new boat slips. | $4,000.00 |
(II) 25 to 49 new boat slips. | $4,000.00 |
(III) 10 to 24 new boat slips. | $2,480.00 |
(IV) 3 to 9 new boat slips. | $830.00 |
(V) 0 to 2 new boat slips. | $500.00 |
c. Short form construction projects involving dredging or filling of 9.99 acres or less of jurisdictional area, pursuant to subsection 62-312.070(2), F.A.C. | $830.00 |
d. Short form construction projects involving the construction of new docking or boardwalk facilities, pursuant to Rule 62-312.070, F.A.C., that provide: | |
(I) 0 to 2 new boat slips. | $500.00 |
(II) 3 to 9 new boat slips. | $830.00 |
(III) The addition of 3 to 20 docking slips to existing functional docking facilities where the total facility will not exceed 50 slips and the existing and proposed slips are not associated with commercial facilities or facilities which provide supplies or services required for boating activities. | $760.00 |
e. Short form and standard form projects solely for environmental restoration or enhancement activities, provided such activities are not associated with a mitigation bank and are not being implemented as mitigation for other activities that require a permit under Part IV of Chapter 373, F.S. | $250.00 |
a. Short form permits from 6 years up to and including 10 years. | $4,950.00 |
b. Standard form permits for 6 years. | $10,650.00 |
c. Standard form permits for 7 years. | $12,430.00 |
d. Standard form permits for 8 years. | $14,200.00 |
e. Standard form permits for 9 years. | $15,980.00 |
f. Standard form permits for 10 years. | $17,750.00 |
g. Standard form permits for 11 years. | $19,530.00 |
h. Standard form permits for 12 years. | $21,300.00 |
i. Standard form permits for 13 years. | $23,080.00 |
j. Standard form permits for 14 years. | $24,850.00 |
k. Standard form permits for 15 years. | $25,000.00 |
l. Standard form permits for 16 years. | $25,000.00 |
m. Standard form permits for 17 years. | $25,000.00 |
n. Standard form permits for 18 years. | $25,000.00 |
o. Standard form permits for 19 years. | $25,000.00 |
p. Standard form permits for 20 years. | $25,000.00 |
q. Standard form permits for 21 years. | $25,000.00 |
r. Standard form permits for 22 years. | $25,000.00 |
s. Standard form permits for 23 years. | $25,000.00 |
t. Standard form permits for 24 years. | $25,000.00 |
u. Standard form permits for 25 years. | $25,000.00 |
v. 6 to 10-year permits for beach restoration projects approved pursuant to Chapter 161, F.S., and to maintenance dredge navigation channels, port harbors, turning basins and harbor berths located within deepwater ports, pursuant to Section 403.816, F.S. | $5,000.00 |
w. Permits for phosphate and attapulgite mines with a duration of greater than 25 years pursuant to the provisions of Section 373.414(15), F.S. | $25,000.00 |
x. Modifications involving permits issued pursuant to Section 403.816, F.S., or Chapter 62-45, F.A.C. | $1,000.00 |
y. 6 to 25-year permits pursuant to Chapter 62-45, F.A.C., and all permits under Section 403.816, F.S. | $5,000.00 |
z. Short form and standard form projects solely for environmental restoration or enhancement activities, provided such activities are not associated with a mitigation bank and are not being implemented as mitigation for other activities that require a permit under Part IV of Chapter 373, F.S. | $250.00 |
a. Mitigation Bank Permit, other than Conceptual Approval Permit. | $6,050.00 |
b. Credit Release (credit available for sale). | $330.00 |
c. Credit Withdrawal (actual use of credit). | $0.00 |
d. Mitigation Bank Conceptual Approval Permit. | $6,050.00 |
e. Major modifications involving changes to one or more of the following components: service area; credit assessment; success or release criteria; hydrologic structures or alterations; construction or mitigation design that does not increase the project area; elimination of lands; or monitoring or management plans: | |
(I) Affecting one of the above components. | $1,340.00 |
(II) Affecting two of the above components. | $2,680.00 |
(III) Affecting three of the above components. | $4,020.00 |
a. Major modifications of Standard Form and Short Form Permits, as determined by Rule 62-312.100, F.A.C., and mitigation banks under Chapter 62-342, F.A.C., that increase the project area or involve four or more of the components listed in sub-subparagraph 62-4.050(4)(e) 3.e., F.A.C., other than for Class I solid waste disposal facilities or as otherwise specified above | Same fee as for a new application for the activity |
b. Minor modifications of Standard Form and Short Form Permits, including mitigation banks, where the modification will not require substantial technical evaluation by the Department, will not lead to substantially different environmental impacts or will lessen the impacts of the original permit, and as further determined by Rule 62-312.100, F.A.C., other than for Class I solid waste disposal facilities or as otherwise specified above: | |
(I) To correct minor errors or typographical mistakes and that do not involve technical review. | $0.00 |
(II) To incorporate changes requested by the Department or required through permits issued by other regulatory agencies, and to change due dates for reporting or performance deadlines when such changes in the due date do not involve any new work, any new work locations, or any new activities, and will not alter, replace, or otherwise eliminate the requirements for otherwise performing the work required by the permit. | $0.00 |
(III) That consist of transfers of permits or time extensions. | $80.00 |
(IV) That consist of minor technical changes which involve new work, new work locations, new activities, or any other change which alters, replaces, or otherwise eliminates the work authorized by the permit when the original permit fee of the issued permit is less than $300, except for modifications to permits issued pursuant to Section 403.816, F.S. | $250.00 |
(V) That consist of minor technical changes which involve new work, new work locations, new activities, or any other change which alters, replaces, or otherwise eliminates the work authorized by the permit when the original permit fee of the issued permit is more than or equal to $300, except for permits issued pursuant to Section 403.816, F.S. | $420.00 |
(VI) For minor modifications for Class I solid waste disposal facilities. | $2,110.00 |
a. Under Section 403.812, F.S. | |
(I) From the prohibition of subsection 62-312.080(7), F.A.C. | $170.00 |
(II) Other variances. | $830.00 |
b. Under Section 120.542, F.S. | $0.00 |
8. Verification of qualification to use a general permit, except: | $250.00 |
a. Paving of existing municipally owned roads under Rule 62-312.824, F.A.C. | $0.00 |
b. Environmental enhancement and restoration activities conducted by the U.S. Army Corps of Engineers under Rule 62-312.825, F.A.C. | $0.00 |
9. Verification that an activity is exempt from regulation under Section 403.813, F.S., or Part IV of Chapter 373, F.S. | $100.00 |
1. Alteration of less than 20 mangroves under Section 403.9328, F.S. | $420.00 |
2. Alteration of 20 or more mangroves under Section 403.9328, F.S. | $830.00 |
3. General Permit under Section 403.9327, F.S. | $250.00 |
4. Verification of an exemption for trimming or alteration. | $0.00 |
5. Minor modification, other than transfer & time extensions. | $250.00 |
6. Transfer of ownership or permit. | $90.00 |
7. Time extension. | $90.00 |
8. Variance under Section 403.9333, F.S. | $170.00 |
1. Notice to use stormwater general permit per paragraphs 62-25.801(1)(a) through (d), F.A.C. | $420.00 |
2. Conversion of construction permit to operation. | $100.00 |
1. Activities qualifying for an Agency's electronic self-certification: | |
a. Self-certification in accordance with the general permit under Section 403.814(12), F.S. | $0.00 |
b. Self-certification for activities other than those under Section 403.814(12), F.S. | $0.00 |
2. Determination of qualification for an activity exemption: | |
a. Under Rules 62-330.050 and 62-330.051, F.A.C. | $100.00 |
b. Under Rule 62-330.0511, F.A.C. | $0 |
3. Determination of qualification to use a general permit. | $250.00 |
4. Individual or conceptual approval permit, excluding permits for a mitigation bank: | |
a. New application - the processing fee for a new permit application shall be as determined from the categories below: | |
(I) Total project area of less than 10 acres and less than 1 acre of works in, on, or over wetlands and other surface waters, and less than 10 new boat slips. | $420.00 |
(II) Project exceeds any of the thresholds in 4.a.(I), above, but involves a total project area of less than 40 acres, less than 3 acres of works in, on, or over wetlands and other surface waters, and less than 30 new boat slips. | $1,500.00 |
(III) Project exceeds any of the thresholds in 4.a.(II), above, but involves a total project area of less than 100 acres, less than 10 acres of works in, on, or over wetlands and other surface waters, and less than 50 new boat slips. | $5,000.00 |
(IV) Project exceeds any of the thresholds in 4.a.(III), above, but involves a total project area of less than 640 acres, and less than 50 acres of works in, on, or over wetlands and other surface waters. | $9,000.00 |
(V) Project exceeds any of the thresholds in 4.a.(IV), above. | $14,000.00 |
(VI) Project exclusively for agricultural or silvicultural purposes; the fee for projects that are solely for agricultural or silvicultural purposes shall be the same as that required by the Water Management District in which the majority of the project area is located, in accordance with Rule 40A-44.201, F.A.C, (7-1-98) incorporated by reference herein (http://www.flrules.org/Gateway/reference.asp?No=Ref-02680), and Rules 40B-1.706, 40C-1.603, 40D-1.607, or 40E-1.607, F.A.C., as applicable, as incorporated by reference in Rule 62-330.071, F.A.C. | The fee shall be the same as that required by the Water Management District in which the majority of the project area is located. |
(VII) Individual or conceptual approval permit solely for environmental restoration or enhancement, provided such activities are not associated with a mitigation bank and are not being implemented as mitigation for other activities that require a permit under Part IV of Chapter 373, F.S. For purposes of this provision, the term "environmental restoration or enhancement" means an action or actions designed and implemented solely to convert degraded or altered uplands, wetlands, or other surface waters to intact communities typical of those historically present, or to improve the quality and condition of currently degraded wetlands or other surface waters to a more healthy, functional, and sustaining condition for fish, wildlife, and listed species. | $250.00 |
(VIII) Individual or conceptual approval permit solely to retrofit an existing stormwater management system or to add treatment to and reduce stormwater pollutant loadings from an existing stormwater management system. | $250.00 |
(IX) Individual permit to construct, alter, maintain or operate a project that is consistent with a valid conceptual approval permit. | 50% of the fee otherwise required for an individual permit under sub-sub-subparagraphs 4.a.(I) through (VIII), above, but not below the minimum required processing fee of $250.00. |
b. Major modification exceeding any of the thresholds in subsection 62-330.315(3), F.A.C. | Same fee as for new permit for the same activity under sub-sub-subparagraphs 4.a.(I) through (IX), above. |
5. Individual or conceptual approval permit for a mitigation bank: | |
a. New application. | $6,050.00 |
b. Major modification exceeding any of the thresholds in subsection 62-330.315(3), F.A.C.: | |
(I) Major modification affecting one of the following: the service area, credit assessment, success or release criteria, hydrologic structures or alterations, elimination of lands, monitoring or management plans, or construction or mitigation design that does not increase the project area. | $1,340.00 |
(II) Affecting two of the components in sub-sub-subparagraph 5.b.(I), above. | $2,680.00 |
(III) Affecting three of the components in sub-sub-subparagraph 5.b.(I), above. | $4,020.00 |
(IV) All other major modifications. | $6,050.00 |
c. Mitigation bank credit release. | $330.00 |
d. Mitigation bank credit withdrawal. | $0.00 |
6. Minor modification of an individual or conceptual approval permit, including a permit for a mitigation bank, that does not exceed any of the thresholds in subsection 62-330.315(3), F.A.C.: | |
a. Extension of permit duration, where not exempt from payment of fees under Florida Statutes. | $80.00 |
b. To correct minor errors that do not involve technical review. | $0.00 |
c. To transfer ownership of a permit or to transfer the permit to an operation and maintenance entity. | $0.00 |
d. All other minor modifications. | $250.00 |
7. Variance or waiver: | |
a. Under Section 120.542, F.S. | $0.00 |
b. Under Section 373.414(17), F.S. | $170.00 |
8. Fee reductions: | |
a. Applications for an individual or conceptual approval permit or modification thereof submitted using the Agency's electronic application system where the processing fee in subparagraph (h)4. or 5., above, exceeds $250.00. | Fee shall be reduced by $100.00, but not below the minimum required processing fee of $250.00. |
b. Applications for any activity by an entity qualifying under Section 218.075, F.S. when the fee under paragraph (h), exceeds $100.00. | $100.00 |
c. Applications for any activity when submitted by the U.S. Department of Defense. | $0.00 |
a. Total area to be included in the determination is up to 1 acre. | $100.00 |
b. Additional fee per acre (or portion thereof) beyond the first acre; total fee not to exceed $500.00. | $50.00 |
a. Total area to be included in the determination is less than 10 acres. | $780.00 |
b. Total area to be included in the determination is at least 10, but less than 40 acres. | $1,060.00 |
c. Total area to be included in the determination is at least 40, but no more than 100 acres. | $2,110.00 |
d. Additional fee per 100 acres (or portion thereof) beyond the first 100 acres. | $290.00 |
3. Reissuance of a formal determination, in accordance with section 7.2.4 of Applicant's Handbook Volume I. | $350.00 |
1. Construction permit for a Class I facility. | $10,000.00 |
2. Construction permit for a Class II facility. | $10,000.00 |
3. Construction permit for a Class III facility. | $6,000.00 |
4. Construction permit for a waste-to-energy facility not covered by the Electric Power Plant Siting Act. | $10,000.00 |
5. Construction permit for other resource recovery facilities. | $2,000.00 |
6. Construction permit for an incinerator. | $3,000.00 |
7. Construction permit for a yard trash composting facility. | $2,000.00 |
8. Construction permit for a manure composting facility. | $2,000.00 |
9. Construction permit for a solid waste composting facility. | $5,000.00 |
10. Construction/operation permit for a waste tire processing facility. | $1,250.00 |
11. Construction permit for all other solid waste facilities. | $1,000.00 |
12. Construction permit for an off-site Biohazardous Waste Treatment Facility other than a biohazardous waste incinerator. | $2,000.00 |
13. Construction permit and/or an operation permit for a facility which has multiple solid waste management components which normally would require individual solid waste permits. A single application may be submitted and the permit fee will be the sum of each individual permit; however, the total permit fees for the facility shall not exceed $25,000, exclusive of modifications and renewals. | |
14. Operation permit for a Class I facility. | $10,000.00 |
15. Operation permit for a Class II facility. | $10,000.00 |
16. Operation permit for a Class III facility. | $4,000.00 |
17. Operation permit for a waste-to-energy facility not covered by the Electric Power Plant Siting Act. | $10,000.00 |
18. Operation permit for other resource recovery facilities. | $1,000.00 |
19. Operation permit for an incinerator. | $1,000.00 |
20. Operation permit for a yard trash composting facility. | $1,000.00 |
21. Operation permit for a manure composting facility. | $1,000.00 |
22. Operation permit for a solid waste composting facility. | $3,000.00 |
23. Operation permit for an offsite Biohazardous Waste Treatment Facility other than a biohazardous waste incinerator. | $1,000.00 |
24. Operation permit for all other solid waste facilities. | $500.00 |
25. Request for an Alternate Procedure. | |
a. Landfill | $2,000.00 |
b. Other | $500.00 |
26. Research, Development and Demonstration permits (one year permit). | $1,000.00 |
27. Closure permit for a Class I facility. | $7,500.00 |
28. Closure permit for a Class II facility. | $7,500.00 |
29. Closure permit for a Class III facility. | $4,000.00 |
30. Closure permit for all other solid waste facilities. | $1,000.00 |
31. Renewal of Closure permit for landfills which address only long term care. | $1,000.00 |
32. Construction or Operation permits for Materials Recovery Facility. | $2,000.00 |
33. Ground Water Monitoring Plan Approvals for solid waste landfills with no other Department permit. | $500.00 |
1. Soil thermal treatment - mobile. | $500.00 |
2. Soil thermal treatment - stationary. | $500.00 |
1. Construction of container and/or tank hazardous waste storage facilities. | $15,000.00 |
2. Construction of container and/or tank hazardous waste storage and treatment facilities. | $20,000.00 |
3. Construction of landfill, surface impoundment, waste pile, land treatment, and miscellaneous unit facilities. | $25,000.00 |
4. Construction of hazardous waste storage, treatment and/or disposal facilities with an incinerator, boiler or industrial furnace for treatment of hazardous wastes generated onsite. | $25,000.00 |
5. Construction of commercial treatment, storage, and/or disposal facility with a commercial incinerator, boiler or industrial furnace managing hazardous wastes generated off-site. | $32,500.00 |
6. Operation of container and/or tank hazardous waste storage facilities. | $10,000.00 |
7. Operation of container and/or tank hazardous waste storage and treatment facilities. | $10,000.00 |
8. Operation of landfill, surface impoundment, waste pile, land treatment, and miscellaneous unit facilities. | $15,000.00 |
9. Operation of hazardous waste storage, treatment and/or disposal facilities with an incinerator, boiler or industrial furnace for treatment of hazardous wastes generated on-site. | $15,000.00 |
10. Operation of commercial treatment, storage, and/or disposal facilities with a commercial incinerator, boiler or industrial furnace managing hazardous wastes generated off-site. | $32,500.00 |
11. Closure of container and/or tank hazardous waste storage facilities. | $10,000.00 |
12. Closure of container and/or tank hazardous waste storage and treatment facilities. | $10,000.00 |
13. Closure of landfill, surface impoundment, waste pile, land treatment, previously closed units required to demonstrate equivalent clean closure, and miscellaneous unit facilities. | $20,000.00 |
14. Closure of hazardous waste storage, treatment and/or disposal facilities with an incinerator, boiler or industrial furnace for treatment of hazardous wastes generated on-site. | $15,000.00 |
15. Closure of commercial treatment, storage, and/or disposal facilities with a commercial incinerator, boiler or industrial furnace managing hazardous wastes generated off-site. | $32,500.00 |
16. Hazardous waste research, development and demonstration facilities. | $4,000.00 |
17. Fees for modifications to hazardous waste permits proposed by the permittee or required by Department rules shall be determined as stated below. All modifications listed below require public notice. Contact the appropriate District Office for guidance on how to determine which fee applies before submitting the required information. | |
a. Substantial modifications that require significant changes to the existing permit and require an extensive evaluation by the Department. These shall require the same fee as a new application. Examples in this category include alteration of the existing facility, change in the facility plan, ground water monitoring program assessment or remediation/engineering design or other general facility standard. The fee schedule for new permit applications is listed above. | |
b. Substantial modifications that require a moderate technical evaluation by the Department. Examples in this category include alterations of the existing facility or its operation which will require additional site-specific evaluation. | $10,000.00 |
c. Moderate modifications that require moderate technical evaluation by the Department. These require a new site inspection, lead to different environmental impacts, or lessen the impacts of the original permit. | $5,000.00 |
d. Minor modifications, as defined in this subsection, that are not otherwise specified, including common or frequently occurring changes needed to maintain a facility's capacity to manage wastes safely, minor changes in ground water monitoring plans, or modifications to conform to new requirements. | $1,000.00 |
18. Department variance from federal regulations under 40 C.F.R. 260.30. | $32,500.00 |
19. All other hazardous waste facility permits or authorizations for which a specific fee is not specified. | $32,500.00 |
1. Construction permit for each Class I test/injection well. | $12,500.00 |
2. Construction permit for each Class I exploratory well. | $5,000.00 |
3. Construction permit for each monitoring well associated with a Class I injection facility when not permitted under a Class I exploratory well or Class I test/injection well permit. | $1,000.00 per well not to exceed $10,000.00 for the facility. |
4. Permit to convert each well from a Class I to a Class V well. | $10,000.00 |
5. Operation permit for each Class I well. | $10,000.00 |
6. Permit to convert a Class I injection well or exploratory well to a monitoring well when not proposed under a construction permit. | $500.00 |
7. Abandonment permit for each Class I well. | $100.00 |
8. Construction permit for each Class III well. | $1,000.00 |
9. Operation permit for each Class III well. | $1,000.00 |
10. Abandonment permit for each Class III well. | $100.00 |
11. Construction permit for each Class V well. | $750.00 |
12. Operation permit for each Class V well. | $750.00 |
13. Abandonment permit for each Class V well. | $25.00 |
14. General permit for each Class V well. | |
a. General permits requiring Professional Engineer or Professional Geologist certification. | $250.00 |
b. General permits not requiring Professional Engineer or Professional Geologist certification. | $25.00 |
15. Major modifications are modifications to an injection facility requiring substantial technical evaluation by the Department, and which will not lead to substantially different environmental impacts (unless those impacts will lessen the impacts of the original permit). | |
a. Major modification to a Class I injection facility. | $1,000.00 |
b. Major modification to a Class III injection facility. | $500.00 |
c. Major modification to a Class V injection facility. | $250.00 |
16. Minor modifications are modifications to an injection facility that do not require a substantial technical evaluation by the Department, will not result in increased capacity of the injection system, do not require a new site inspection by the Department, and will not lead to substantially different environmental impacts or will lessen the impacts of the original permit. | |
a. Minor modification to a Class I or Class III injection facility. | $250.00 |
b. Minor modification to a Class V injection facility. | $100.00 |
17. Rerating of the permitted capacity of a Class I injection well to the maximum injection velocity allowed under paragraph 62-28.230(1)(e), F.A.C. | $250.00 |
a. Treatment plant - 5 MGD and above. | $12,500.00 |
b. Treatment plant - 1 MGD up to 5 MGD. | $10,000.00 |
c. Treatment plant - 0.25 MGD up to 1 MGD. | $7,000.00 |
d. Treatment plant - 0.1 MGD up to 0.25 MGD. | $4,000.00 |
e. Treatment plant - up to 0.1 MGD. | $2,000.00 |
a. Treatment plant - 5 MGD and above. | $12,500.00 |
b. Treatment plant - 1 MGD up to 5 MGD. | $10,000.00 |
c. Treatment plant - 0.25 MGD up to 1 MGD. | $7,000.00 |
d. Treatment plant - 0.1 MGD up to 0.25 MGD. | $4,000.00 |
e. Treatment plant - .01 MGD up to 0.1 MGD. | $2,000.00 |
f. Treatment plant - up to 0.01 MGD. | $800.00 |
a. Treatment plant - 5 MGD and above. | $10,000.00 |
b. Treatment plant - 1 MGD up to 5 MGD. | $6,000.00 |
c. Treatment plant - 0.25 MGD up to 1 MGD. | $2,000.00 |
d. Treatment plant - up to 0.25 MGD. | $1,000.00 |
e. Treatment plant - up to 0.1 MGD. | $600.00 |
a. Serving a community public water system. | $900.00 |
b. Serving a non-transient non-community public water system. | $700.00 |
c. Serving a non-community public water system. | $500.00 |
5. Construction permit for each public water supply well. | |
a. Well located in a delineated area pursuant to Chapter 62-524, F.A.C. | $1,000.00 |
b. Any other public water supply well. | $500.00 |
a. 1 MGD and above. | $4,000.00 |
b. 0.1 MGD up to 1 MGD. | $2,000.00 |
c. 0.01 MGD up to 0.1 MGD. | $1,000.00 |
d. Up to 0.01 MGD. | $500.00 |
7. Minor modifications to systems that result in no change in the treatment or capacity. | |
a. 0.1 MGD and above. | $1,000.00 |
b. Up to 0.1 MGD. | $500.00 |
8. General Permit fee for any General Permit not specifically in subparagraphs 1. through 7. above: a. General permits requiring Professional Engineer or Professional Geologist certification. | $650.00 |
b. General permits not requiring Professional Engineer or Professional Geologist certificaiton. | $500.00 |
1. General permits requiring Professional Engineer or Professional Geologist certification. | $250.00 |
2. General permits not requiring Professional Engineer or Professional Geologist certification. | $100.00 |
1. Site specific alternative criteria for each application. | $15,000.00 |
2. Variance or exemption for each water quality criteria. | $6,000.00 |
3. Variance or exemption for public water system from maximum contaminant level/treatment techniques. | $1,000.00 |
4. Variance from other permitting standards or conditions. | $2,000.00 |
5. Aquifer exemption - major. | $15,000.00 |
6. Aquifer exemption - minor. | $7,500.00 |
(r) Permits to construct or operate any other type of facility or stationary installation not specifically listed in paragraphs (a) through (n). | $100.00 |
1. To correct minor errors or typographical mistakes and that do not involve technical review. | $0.00 |
2. To incorporate changes requested by the Department or required through permits issued by other regulatory agencies, and to change due dates for reporting or performance deadlines when such changes in the due date do not involve any new work, any new work locations, or any new activities, and will not alter, replace, or otherwise eliminate the requirements for otherwise performing the work required by the permit. | $0.00 |
3. That consist of transfers of permits or time extensions. | $50.00 |
4. That consist of minor technical changes which involve new work, new work locations, new activities, or any other change which alters, replaces, or otherwise eliminates the work authorized by the permit when the original permit fee of the issued permit is less than $300, except for modifications to permits issued pursuant to Section 403.816, F.S. | $50.00 |
5. That consist of minor technical changes which involve new work, new work locations, new activities, or any other change which alters, replaces, or otherwise eliminates the work authorized by the permit when the original permit fee of the issued permit is more than or equal to $300, except for Domestic Wastewater Facility Permits, Industrial Wastewater Facility Permits, Drinking Water (Public Water Supply) Permits, Underground Injection Control Permits and permits issued pursuant to Section 403.816, F.S. | $250.00 |
Fla. Admin. Code Ann. R. 62-4.050
Rulemaking Authority 373.026, 373.043, 373.109, 373.4131, 373.414, 373.418, 373.421, 403.061, 403.087, 403.704(30), 403.805 FS. Law Implemented 373.109, 373.309, 373.409, 373.413, 373.4135, 373.414(9), (11), (12)(a), (13), (14), (15), (16), 373.4145, 373.418, 373.421, 403.061, 403.087, 403.0877, 403.088, 403.0885, 403.722, 403.861(7) FS.
New 5-17-72, Amended 6-19-74, 7-8-82, Formerly 17-4.05, Amended 11-15-87, 8-31-88, 10-3-88, 4-4-89, 3-19-90, 6-11-90, 3-7-91, 3-18-91, 5-30-91, 10-30-91, 11-16-92, 12-21-92, 7-11-93, 2-2-94, Formerly 17-4.050, Amended 11-23-94, 4-30-95, 7-4-95, 12-15-98, 10-22-00, 6-1-01, 1-30-03, 2-19-03, 4-3-03, 5-1-03, 2-7-06, 10-31-07, 4-21-09, 5-9-13, 10-1-13, 2-17-16.