D.C. Mun. Regs. tit. 5, r. 5-D113

Current through Register Vol. 71, No. 49, December 6, 2024
Rule 5-D113 - COST REIMBURSEMENT CONTRACTS
113.1

Cost reimbursement contracts provide for the contractor to recover the reimbursable costs it incurs in contract performance, plus a fee (that is, a profit).

113.2

A reimbursable cost must be:

(a) Reasonable in nature and amount;
(b) Properly allocable to the contract;
(c) Determined in accordance with generally accepted accounting principles; and
(d) Not identified as nonreimbursable under the terms of the particular contract.
113.3

To ensure that the Office's payment obligations are not open-ended, a cost reimbursement contract must specify an estimated total cost that the contractor cannot exceed (the "not-to-exceed limit"), except at its own risk, without the Contracting Officer's written approval. Because the contractor can cease performance once it reaches the estimated total cost (unless the Contracting Officer approves an increase), it is not obligated to complete the contract work unless it can do so within the not-to-exceed limit.

113.4

Cost reimbursement contracts can take three (3) forms:

(a) Cost-plus-fixed-fee;
(b) Cost-plus-incentive-fee; and
(c) Cost-plus-award-fee.
113.5

The differences between the types of cost reimbursement contracts listed in Section 113.4 relate to the manner in which the contractor's fee is determined.

113.6

A cost-plus-fixed-fee contract provides for a fee that is fixed at the contract's inception and is not subject to adjustment unless the contract is modified to change the contract work.

113.7

A cost-plus-incentive-fee contract provides for a fee that generally is determined by applying a formula based on the relationship between the contractor's total reimbursable cost and a total target cost, subject to a specified minimum and maximum. These contracts also can include incentive formulas based on the contractor's schedule or technical performance.

113.8

A cost-plus-award-fee contract provides for:

(a) A base fee fixed at the contract's inception; and
(b) An award fee that the contractor may earn (in whole or in part) during performance, which is designed to motivate superior performance.
113.9

The award fee in a cost-plus-award-fee contract is determined unilaterally by the Office, based on its judgment and evaluation of how well the contractor has performed in relation to the award fee criteria identified in the contract. In no event shall the total award fee available to the contractor exceed ten percent (10%).

113.10

In appropriate circumstances, the Office may include a guaranteed maximum price ("GMP") in a cost reimbursement contract. A GMP differs from a not-to-exceed amount in that a contractor is required to complete performance of the base scope of work required under the contract for an amount that does not exceed the GMP. Under such an approach, if the total cost exceeds the GMP, the contractor shall be required to complete performance of the base scope of work at its own cost and expense.

D.C. Mun. Regs. tit. 5, r. 5-D113

Notice of Emergency and Proposed Rulemaking published at 57 DCR 8514 (September 17, 2010) [EXPIRED]; as amended by Notice of Final Rulemaking published at 57 DCR 11189, 11200 (November 26, 2010)
Authority: The Director of the Office of Public Education Facilities Modernization, pursuant to section 702(b) of the District of Columbia Public Education Reform Amendment Act of 2007 (Act), effective June 12, 2007 (D.C. Law 17-9; D.C. Official Code § 38-451(b)) (2007 Supp.).