D.C. Mun. Regs. tit. 27, r. 27-4104

Current through Register Vol. 71, No. 49, December 6, 2024
Rule 27-4104 - PROVISION OF MATERIAL FOR PERFORMING CONTRACTS
4104.1

Except as provided otherwise in this section, each contractor and subcontractor shall furnish all material for performing District contracts.

4104.2

The contracting officer may provide material to the contractor or subcontractor when necessary to achieve significant economy, standardization, expedited production, or when it is otherwise determined to be in the best interest of the District.

4104.3

The solicitation shall specify material that the District will furnish in sufficient detail to enable offerors to accurately evaluate and respond to the solicitation.

D.C. Mun. Regs. tit. 27, r. 27-4104

Final Rulemaking published at 35 DCR 1738 (February 26, 1988); amended by Final Rulemaking published at 63 DCR 10016 (7/29/2016)