D.C. Mun. Regs. tit. 27, r. 27-3222

Current through Register Vol. 71, No. 49, December 6, 2024
Rule 27-3222 - PROTECTION OF DISTRICT TITLE
3222.1

The contracting officer shall include a provision, approved by the Director, with the progress payment provisions in the contract which provides that the District shall receive title to all of the materials, work-in-progress, finished goods, and other items of property under the contract.

3222.2

The contracting officer shall ensure that District title is not compromised by other encumbrances, liens, or hypothecations.

3222.3

The contracting officer shall require additional protective provisions, if deemed necessary, to establish and protect the District's title.

D.C. Mun. Regs. tit. 27, r. 27-3222

Final Rulemaking published at 35 DCR 1636 (February 26, 1988)