If a contract is modified, the contracting officer shall obtain the consent of surety in the following circumstances:
The contracting officer shall obtain the consent of surety for a novation agreement.
The contracting officer shall obtain the consent of surety when a contract is to be awarded after the deadline set for contract award unless the written commitment of the surety extends to or beyond the date the contract is signed.