The Commission may award sole source contracts where there is a reasonable basis to conclude that the Commission's needs can only be satisfied by the goods, services, or construction proposed to be procured and when the proposed sole source contract is the only source capable of providing the required goods, services, or construction.
A reasonable basis sufficient to justify sole source contracts may include, but are not limited to:
Sole source procurements shall not be justified solely on the basis of any of the following:
The CCO shall take all reasonable steps to avoid using sole source procurements.
For each sole source procurement, the CCO shall be required to provide the Board of Directors with a prior written determination that the minimum needs of the Commission can only be met by the goods, services or construction sought to be procured on a sole source basis and that the proposed sole source is the only source capable of providing same.
The CCO's written determination shall include the following:
The CCO shall include all applicable standard contract clauses in any procurement made under this section.
D.C. Mun. Regs. tit. 19, r. 19-2805