Current through Register Vol. 71, No. 49, December 6, 2024
Rule 11-C501 - PERVIOUS SURFACE REQUIREMENT501.1 The minimum pervious surface percentage shall be as required by the development standards for the R and RF zones.
501.2 The minimum pervious surface percentage requirement shall be applicable only in conjunction with the following:
(a) The construction of a new principal structure;(b) An addition to a principal or accessory structure, other than a historic resource, that increases the existing lot occupancy at the time of building permit application by ten percent (10%) or more;(c) The construction of a new accessory structure that increases the existing lot occupancy at the time of building permit application by ten percent (10%) or more; or(d) An addition to a historic resource that increases the existing lot occupancy at the time of building permit application by twenty-five percent (25%) or more.D.C. Mun. Regs. tit. 11, r. 11-C501
Final Rulemaking published at 63 DCR 2447 (9/6/2016)