Current through Reigster Vol. 28, No. 6, December 1, 2024
Section 1302-264-N-264.310 - Closure and Post-closure Care(a) At final closure of the landfill or upon closure of any cell, the owner or operator must cover the landfill or cell with a final cover designed and constructed to: (1) Provide long-term minimization of migration of liquids through the closed landfill;(2) Function with minimum maintenance;(3) Promote drainage and minimize erosion or abrasion of the cover;(4) Accommodate settling and subsidence so that the cover's integrity is maintained; and(5) Have a permeability less than or equal to the permeability of any bottom liner system or natural subsoils present.(b) After final closure, the owner or operator must comply with all post-closure requirements contained in §§ 264.117-264.120, including maintenance and monitoring throughout the post-closure care period (specified in the permit under § 264.117). The owner or operator must: (1) Maintain the integrity and effectiveness of the final cover, including making repairs to the cap as necessary to correct the effects of settling, subsidence, erosion, or other events;(2) Continue to operate the leachate collection and removal system until leachate is no longer detected;(3) Maintain and monitor the leak detection system in accordance with §§ 264.301 (c)(3)(iv) and (4) and 264.303(c), and comply with all other applicable leak detection system requirements of this part;(4) Maintain and monitor the groundwater monitoring system and comply with all other applicable requirements of Subpart F of this part;(5) Prevent run-on and run-off from eroding or otherwise damaging the final cover; and(6) Protect and maintain surveyed benchmarks used in complying with § 264.309. (Amended May 8, 1986, August 1, 1995)
7 Del. Admin. Code § 1302-264-N-264.310