7 Del. Admin. Code § 1302-262-M-262.260

Current through Reigster Vol. 28, No. 6, December 1, 2024
Section 1302-262-M-262.260 - Purpose and implementation of contingency plan
(a) A large quantity generator must have a contingency plan for the facility. The contingency plan must be designed to minimize hazards to human health or the environment from fires, explosions, or any unplanned sudden or non-sudden release of hazardous waste or hazardous waste constituents to air, soil, or surface water.
(b) The provisions of the plan must be carried out immediately whenever there is a fire, explosion, or release of hazardous waste or hazardous waste constituents which could threaten human health or the environment.

7 Del. Admin. Code § 1302-262-M-262.260

24 DE Reg. 711 (1/1/2021)(final)