26 Del. Admin. Code § 1009-3.0

Current through Register Vol. 28, No. 7, January 1, 2025
Section 1009-3.0 - Filing Requirements
3.1 Each DSIC / UFRC filing shall include the following information:
3.1.1 A PSC filing cover sheet (which can be found at the Commission website;
3.1.2 A cover letter from the utility;
3.1.3 The appropriate filing fee as required by 26 Del.C. § 114 (a);
3.1.4 An original application and five (5) copies (Staff reserves the right to request additional copies), which shall include:
3.1.4.1 A request to place rates into effect in no less than thirty (30) days from the date of the application;
3.1.4.2 The new DSIC/UFRC rate expressed as a percentage carried to two (2) decimal places; and
3.1.4.3 The dollar amount and percentage of the proposed DSIC/UFRC rate change.
3.1.5 The identification of a utility contact person responsible for the application.
3.1.6 A DSIC / UFRC Application shall include the following schedules:
3.1.6.1 Schedule 1: Development of rate and supporting data (see Form 1);
3.1.6.2 Schedule 1A: Capital structure approved in the utility's most recent base rate/general rate case (see Form 2);
3.1.6.3 Schedule 1B: Overcollections or Undercollections from the utility's previous DSIC/UFRC filing (see Form 3);
3.1.6.4 Schedule 2 (see Form 4):
3.1.6.4.1 For DSIC Filings: Net cost of projects (identified by utility's internal project number) placed into service, and unreimbursed plant additions and plant retired, for the appropriate DSIC filing period.
3.1.6.4.2 For UFRC Filings: Identification (by utility's internal project number) of relocated unreimbursed utility plant or facilities and plant retired for the appropriate UFRC filing period.
3.1.6.5 Schedule 2A: Net Accumulated Depreciation, identified by NARUC account number for DSIC Filings and by FERC USOA account number for UFRC Filings (see Form 5);
3.1.6.6 Schedule 3: Revised tariff page(s). Additions should be indicated by underlining; deletions should be indicated by strikethroughs.
3.2 The utility shall serve the Division of the Public Advocate's office with a copy of the Filing at the same time that the utility files the Filing with the Commission.
3.3 The utility shall notify its customers of changes in the DSIC or UFRC rate by including appropriate information in the first bill that customers receive following any change in the DSIC or UFRC rate. A message printed directly on the bill shall be acceptable notice.