26 Del. Admin. Code § 3013-3.0

Current through Register Vol. 28, No. 5, November 1, 2024
Section 3013-3.0 - Applications to the Commission
3.1 Before a community energy facility may offer a contract or commence service to a subscriber, and before Delmarva provides the community energy facility with a permission to operate under Section 6.0 of this regulation, the community energy facility must apply for and obtain from the Commission both a preliminary certificate to operate, which establishes project viability, and a final certificate to operate, which establishes compliance with all application requirements.
3.2 Applicants must comply with the electronic filing requirements of 26 DE Admin. Code 1001, "Rules of Practice and Procedure of the Commission".

26 Del. Admin. Code § 3013-3.0

27 DE Reg. 987 (6/1/2024) (Final)