26 Del. Admin. Code § 3010-9.0

Current through Register Vol. 28, No. 7, January 1, 2025
Section 3010-9.0 - Review and Comment
9.1 As part of the process commencing in 2009 and continuing on an annual basis, the Company shall submit a report to the Commission, the Governor and the General Assembly detailing their progress in implementing their IRPs.
9.2 The Commission, interested State Agencies, interested parties and the general public shall be provided an opportunity for review and comment on the Company's IRP filings. The Commission shall seek input from DNREC on the issue of externalities and environmental benefits due to emissions, as the result of the proposed IRP.
9.3 Subsequent to the IRP recognition and after input from the public, and other parties, the Commission may ratify the filing of the Company's IRP and its compliance with these regulations. Ratification that the IRP complies with the statute shall not guarantee a particular ratemaking treatment of future resource acquisitions. To the extent that the Commission determines that the IRP is not compliant with the statute or is unlikely to meet the goals of the statute, the Company shall revise its IRP to meet these requirements. Rate treatment shall be addressed in rate or other proceedings as filed by the utility or as initiated by the Commission.
9.4 The Integrated Resource Plan may be used as a factor in rate cases to evaluate the performance of the utility. Reports provided under this Regulation are subject to annual review and audit by the Commission and interested State Agencies. The Company must maintain sufficient records to permit a review and confirmation of material contained in all required reports.

26 Del. Admin. Code § 3010-9.0

13 DE Reg. 953 (01/01/10)