Current through October 16, 2024
Section 17-31z-14 - Execution of project(a) The Department shall be notified of the date and time of the construction contract signing. After the contract signing, the applicant shall submit to the Department: (1) One copy of the Executed Contract;(2) One copy of each: Performance Bond; Labor and Material Payment Bond and Power of Attorney for Surety.(3) One copy of contractor's certificate of Insurance.(b) The Department shall be notified of date of "groundbreaking" and subsequent work schedule for the facility. Department staff may make periodic site visits during construction and may attend job meetings.(c) The Department shall be notified as soon as it is evident that delays in construction may require a budget period extension.Conn. Agencies Regs. § 17-31z-14