Section 4 CCR 723-4-4210 - Line Extension
(a) A utility shall have tariffs which set out its line extension policies, procedures, and conditions.
(b) In its tariff a LDC shall include the following provisions for gas main extensions and service lateral extensions from its distribution system:
(I) the terms and conditions, by customer class, under which an extension will be made;
(II) provisions requiring the utility to provide to a customer or to a potential customer, upon request, service lateral connection information necessary to allow the customer's or potential customer's facilities to be connected to the utility's system;
(III) provisions requiring the utility to exercise due diligence in providing the customer or potential customer with an estimate of the anticipated cost of a connection or extension; and
(IV) provisions addressing steps to ameliorate the rate and service impact upon existing customers, including stating in the tariff the procedures by which future customers would share costs incurred by the initial or existing customers served by a connection or extension (as, for example, by including the procedures by which a refund of customer connection or extension payments would be made when appropriate).

4 CCR 723-4-4210

38 CR 17, September 10, 2015, effective 9/30/2015
40 CR 01, January 10, 2017, effective 1/30/2017
41 CR 11, June 10, 2018, effective 6/30/2018
42 CR 07, April 10, 2019, effective 4/30/2019
43 CR 08, April 25, 2020, effective 5/15/2020
44 CR 04, February 25, 2021, effective 3/17/2021
44 CR 24, December 25, 2021, effective 1/14/2022
45 CR 18, September 25, 2022, effective 10/15/2022
46 CR 06, March 25, 2023, effective 1/25/2023
46 CR 08, April 25, 2023, effective 5/15/2023