4 Colo. Code Regs. § 723-4-4702

Current through Register Vol. 47, No. 22, November 25, 2024
Section 4 CCR 723-4-4702 - Precondition to Application

In order for a utility or power authority to appeal a local government action to the Commission pursuant to this rule and pursuant to § 29-20-108, C.R.S., one or more of the following conditions must be met:

(a) the utility or power authority has applied for or has obtained a certificate of public convenience and necessity from the Commission pursuant to § 40-5-101, C.R.S., to construct the major natural gas facility that is the subject of the local government action;
(b) a certificate of public convenience and necessity is not required for the utility or power authority to construct the major natural gas facility that is the subject of the local government action; and
(c) the Commission has previously entered an order pursuant to § 40-4-102, C.R.S., that conflicts with the local government action.

4 CCR 723-4-4702

38 CR 17, September 10, 2015, effective 9/30/2015
40 CR 01, January 10, 2017, effective 1/30/2017
41 CR 11, June 10, 2018, effective 6/30/2018
42 CR 07, April 10, 2019, effective 4/30/2019
43 CR 08, April 25, 2020, effective 5/15/2020
44 CR 04, February 25, 2021, effective 3/17/2021
44 CR 24, December 25, 2021, effective 1/14/2022
45 CR 18, September 25, 2022, effective 10/15/2022
46 CR 06, March 25, 2023, effective 1/25/2023
46 CR 08, April 25, 2023, effective 5/15/2023