Current through Register Vol. 47, No. 22, November 25, 2024
Section 4 CCR 723-4-4702 - Precondition to ApplicationIn order for a utility or power authority to appeal a local government action to the Commission pursuant to this rule and pursuant to § 29-20-108, C.R.S., one or more of the following conditions must be met:
(a) the utility or power authority has applied for or has obtained a certificate of public convenience and necessity from the Commission pursuant to § 40-5-101, C.R.S., to construct the major natural gas facility that is the subject of the local government action;(b) a certificate of public convenience and necessity is not required for the utility or power authority to construct the major natural gas facility that is the subject of the local government action; and(c) the Commission has previously entered an order pursuant to § 40-4-102, C.R.S., that conflicts with the local government action.38 CR 17, September 10, 2015, effective 9/30/201540 CR 01, January 10, 2017, effective 1/30/201741 CR 11, June 10, 2018, effective 6/30/201842 CR 07, April 10, 2019, effective 4/30/201943 CR 08, April 25, 2020, effective 5/15/202044 CR 04, February 25, 2021, effective 3/17/202144 CR 24, December 25, 2021, effective 1/14/202245 CR 18, September 25, 2022, effective 10/15/202246 CR 06, March 25, 2023, effective 1/25/202346 CR 08, April 25, 2023, effective 5/15/2023