R-24-103-401-02

Current through Register Vol. 48, No. 1, January 10, 2025
Section R-24-103-401-02 - Ability to Meet Standards

The prospective contractor or vendor may demonstrate the availability of necessary financing, equipment, facilities, expertise, and personnel by submitting upon request:

(a) Evidence that such contractor possesses such necessary items;
(b) Acceptable plans to subcontract for such necessary items; or
(c) A documented commitment from, or explicit arrangement with a satisfactory source to provide the necessary items.

R- 24-103-401 -03 Written Determination of Non-Responsibility Required

If a prospective contractor or vendor who otherwise would have been awarded a contract is found to be non-responsible, a written determination of non-responsibility setting forth the basis of the finding shall be prepared by the procurement official. A copy of the determination shall be sent promptly to the non-responsible prospective contractor or vendor. The determination shall be made part of the procurement record.

R-24-103-401-02

38 CR 15, August 10, 2015, effective 8/31/2015
41 CR 17, September 10, 2018, effective 10/1/2018
46 CR 11, June 10, 2023, effective 7/1/2023