Under the National Environmental Policy Act, the Agency is required to assess the potential impact of the proposed actions on protected environmental resources. Measures to avoid or mitigate adverse impacts to protected resources may require a change in site or project design. A site will not be approved by the Agency until the Agency has completed the environmental review process in accordance with 7 CFR part 1970 .
7 C.F.R. §3565.255