7 C.F.R. § 1724.56 app A to Subpart E of Part 1724

Current through October 31, 2024
Appendix A to Subpart E of Part 1724 - Hazard Potential Classification for Civil Works Projects

The source for this appendix is U.S. Army Corps of Engineers Engineering and Design Dam Safety Assurance Program, ER 1110-2-1155, Appendix E. Appendix E is available from the address listed in § 1724.55(a)(2) .

Category1 Low Significant High
Direct Loss of Life2None expected (due to rural location with no permanent structures for human habitation)Uncertain (rural location with few residences and only transient or industrial development)Certain (one or more extensive residential, commercial or industrial development).
Lifeline Losses3No disruption of services-repairs are cosmetic or rapidly repairable damageDisruption of essential facilities and accessDisruption of critical facilities and access.
Property Losses4Private agricultural lands, equipment and isolated buildingsMajor public and private facilitiesExtensive public and private facilities.
Environmental Losses5Minimal incremental damageMajor mitigation requiredExtensive mitigation cost or impossible to mitigate.

NOTES:

1 Categories are based upon project performance and do not apply to individual structures within a project.

2 Loss of life potential based upon inundation mapping of area downstream of the project. Analysis of loss of life potential should take into account the extent of development and associated population at risk, time of flood wave travel and warning time.

3 Indirect threats to life caused by the interruption of lifeline services due to project failure, or operation, i.e., direct loss of (or access to) critical medical facilities or loss of water or power supply, communications, power supply, etc.

4 Direct economic impact of value of property damages to project facilities and down stream property and indirect economic impact due to loss of project services, i.e., impact on navigation industry of the loss of a dam and navigation pool, or impact upon a community of the loss of water or power supply.

5 Environmental impact downstream caused by the incremental flood wave produced by the project failure, beyond which would normally be expected for the magnitude flood event under a without project conditions.

7 C.F.R. 1724.56 app A to Subpart E of Part 1724