Section 4284.940 - Processing applications
(a)Initial review. Upon receipt of an application on or before the application submission deadline for each Fiscal Year, the Agency will conduct a review to determine if the Applicant and project are eligible, and if the application is complete and sufficiently responsive to program requirements.
(b)Notifications. After the review in paragraph (a) of this section has been conducted, if the Agency has determined that either the Applicant or project is ineligible or that the application is not complete to allow evaluation of the application or sufficiently responsive to program requirements, the Agency will notify the Applicant in writing and will include in the notification the reason(s) for its determination(s).
(c)Resubmittal by Applicants. Applicants may submit revised applications to the Agency in response to the notification received under paragraph (b) of this section. If a revised grant application is received on or before the application deadline, it will be processed by the Agency. If a revised application is not received by the specified application deadline, the Agency will not process the application and will inform the Applicant that their application was not reviewed due to tardiness.
(d)Subsequent ineligibility determinations. If at any time an application is determined to be ineligible, the Agency will notify the Applicant in writing of its determination.

7 C.F.R. §4284.940