7 C.F.R. § 4280.113

Current through October 31, 2024
Section 4280.113 - Project eligibility

For a project to be eligible to receive a RES or EEI grant under this subpart, the proposed project must meet each of the requirements specified in paragraphs (a) through (e) of this section. Subsequent EEI projects must meet the requirements specified in paragraph (a)(5)(ii) of this section. The applicant is cautioned against taking any actions or incurring any obligations prior to the Agency completing the environmental review that would either limit the range of alternatives to be considered or that would have an adverse effect on the environment, such as the initiation of construction. If the applicant takes any such actions or incurs any such obligations, it could result in project ineligibility.

(a) The project must be for:
(1) The purchase of a new RES;
(2) The purchase of a refurbished RES;
(3) The retrofitting of an existing RES;
(4) For the purposes of this subpart, only those hydroelectric sources with a rated power of 30 megawatts or less are eligible, or
(5) Making an EEI that will allow less energy to be used on an annual basis than the original building and/or equipment being improved or replaced as provided in a vendor/installer certification or as demonstrated in an energy assessment or energy audit as applicable.
(i)Types of improvements. Eligible EEI include, but are not limited to:
(A) Efficiency improvements to existing RES; and
(B) Construction of a new energy efficient building only when the building is used for the same purpose as the existing building, and, based on an energy assessment or energy audit, as applicable, it will be more cost effective to construct a new building and will use less energy on annual basis than improving the existing building.
(ii)Subsequent EEI projects. A proposed EEI project that replaces an EEI project previously funded under this subpart may or may not be eligible for funding.
(A) If the proposed EEI project would replace the same specific EEI equipment that had previously received funds under this subpart prior to the end of the useful life, as specified in the Financial Assistance Agreement, then the proposed improvement project, even if it is more energy efficient than the previously funded improvement, is ineligible.
(B) If the proposed EEI project would replace the same specific EEI equipment that had previously received funds under this subpart at or after the end of the useful life, as specified in the Financial Assistance Agreement, then the proposed improvement is eligible for funding under this subpart provided the EEI is more energy efficient than the previously funded improvement. If the proposed EEI is not more energy efficient than the previously funded improvement, then it is not eligible for funding under this subpart.
(b) The project must utilize commercially available technology;
(c) The project must have technical merit, as determined using the procedures specified in § 4280.117 ; and
(d) The project must be located in a rural area in a State if the type of applicant is a rural small business, or in a rural or non-rural area in a State if the type of applicant is an agricultural producer and the application supports the production, processing, vertical integration, or marketing of agricultural products. If the agricultural producer's operation is in a non-rural area, then the application can only be for RES or EEI components of the business operation that are directly related to and their use and purpose is limited to the agricultural production operation, such as vertically integrated operations, and are part of and co-located with the agricultural production operation.
(e) For a RES project, where a residence is closely associated with and shares an energy metering device with an agricultural operation or rural small business to be served by the RES project, 50 percent or more of the energy to be generated by the RES project must be used by the agricultural operation or rural small business. This also includes projects which will virtually net meter or credit energy to be generated by the RES project to a residence off-site from the project and owned by the applicant. The application must contain sufficient documentation to evaluate this provision which may include using either of the methods identified in paragraphs (e)(1) through (2) of this section.
(1) Provide a renewable energy site assessment or other documentation including calculations that demonstrate, based on historical energy use, that 50 percent or more of the energy to be produced by the RES project will be used in the agricultural operation or rural small business. This includes documentation on historical residential energy use. The Agency may request additional data to determine residential versus business or agricultural operation usage. The actual percentage of energy determined to benefit the rural small business or agricultural operation will be used to determine eligible project costs; or
(2) The applicant may install, or elect to conditionalize funding upon the installation of, a device (such as a second meter) that restricts 100 percent of the energy generated by the RES project to be used only by the agricultural operation or rural small business.
(f) An applicant is permitted to use up to 10 percent of the amount provided under this subpart to construct, improve, or acquire broadband infrastructure, subject to the requirements of 7 CFR 1980 , Subpart M, Special Authority to Enable Funding of Broadband and Smart Utility Facilities Across Select Rural Development Programs.

7 C.F.R. §4280.113

83 FR 30831, 7/2/2018; 86 FR 22309, 7/26/2021