50 C.F.R. § 86.59

Current through September 30, 2024
Section 86.59 - What does the Service consider when evaluating a project for innovative physical components, technology, or techniques that improve the BIG project?
(a) In evaluating a proposed project under the criterion at § 86.51(c)(2) , we consider if the project will include physical components, technology, or techniques that are:
(1) Newly available; or
(2) Repurposed in a unique way.
(b) Examples of the type of innovations we will consider are components, technology, or techniques that:
(1) Extend the useful life of the BIG-funded project;
(2) Are designed to allow the operator to save costs, decrease maintenance, or improve operation;
(3) Are designed to improve BIG-eligible services or amenities;
(4) Reduce the carbon footprint of the BIG-funded facility. Carbon footprint means the impact of the total set of greenhouse gas emissions;
(5) Are used during construction specifically to reduce negative environmental impacts, beyond compliance requirements; or
(6) Improve facility resilience.