49 C.F.R. § 674.29

Current through September 30, 2024
Section 674.29 - Public Transportation Agency Safety Plans: general requirements
(a) In determining whether to approve a Public Transportation Agency Safety Plan for a rail fixed guideway public transportation system, an SSOA must evaluate whether the Public Transportation Agency Safety Plan is consistent with the regulations implementing such Plans; is consistent with the National Public Transportation Safety Plan; and is in compliance with the program standard set by the SSOA.
(b) In determining whether a Public Transportation Agency Safety Plan is compliant with 49 CFR part 673, an SSOA must determine, specifically, whether the Public Transportation Agency Safety Plan is approved by the RTA's board of directors or equivalent entity; sets forth a sufficiently explicit process for safety risk management, with adequate means of risk mitigation for the rail fixed guideway public transportation system; includes a process and timeline for annually reviewing and updating the safety plan; includes a comprehensive staff training program for the operations personnel directly responsible for the safety of the RTA; identifies an adequately trained safety officer who reports directly to the general manager, president, or equivalent officer of the RTA; includes adequate methods to support the execution of the Public Transportation Agency Safety Plan by all employees, agents, and contractors for the rail fixed guideway public transportation system; and sufficiently addresses other requirements under the regulations at 49 CFR part 673.
(c) In an instance in which an SSOA does not approve a Public Transportation Agency Safety Plan, the SSOA must provide a written explanation, and allow the RTA an opportunity to modify and resubmit its Public Transportation Agency Safety Plan for the SSOA's approval.

49 C.F.R. § 674.29

81 FR 14256, 3/16/2016