49 C.F.R. § 299.711

Current through November 30, 2024
Section 299.711 - Inspection, testing, and maintenance program format

The submission to FRA for each identified subsystem shall consist of two parts-

(a) The complete inspection, testing, and maintenance program, in its entirety, including all required information prescribed in § 299.701 , and all information and procedures required for the railroad and its personnel to implement the program.
(b) A condensed version of the program that contains only those items identified as safety-critical, per § 299.703 submitted for approval by FRA under § 299.713 .

49 C.F.R. §299.711

85 FR 69731 , 12/3/2020