49 C.F.R. § 230.37

Current through November 30, 2024
Section 230.37 - Steam test following repairs or alterations

Upon completion of any repair or alteration, the locomotive owner and/or operator shall conduct a steam test of the boiler with steam pressure raised to between 95 percent and 100 percent of the MAWP. At this time, the boiler shall be inspected to ensure that it is in a safe and suitable condition for service.

49 C.F.R. § 230.37