48 C.F.R. § 925.103

Current through October 31, 2024
Section 925.103 - Exceptions
(b)Nonavailabilty -
(2)
(i)Individual determinations. Contracting officers may make the determination required by 48 CFR 25.103(b)(2)(i) , provided such determination is factually supported in writing. If the contract is estimated to exceed $1 million, the Head of the Contracting Activity must approve the determination.
(ii) Proposals to add an article to the list of nonavailable articles at 48 CFR 25.104 , with appropriate justifications, must be submitted for approval by the Senior Procurement Executive and submission to the appropriate council.

48 C.F.R. §925.103

74 FR 36366 , July 22, 2009, as amended at 75 FR 69013 , Nov. 10, 2010; 81 FR 45977 , July 15, 2016