As prescribed in 536.270-5(c), insert a provision substantially the same as the following provision:
Basis of Award-Sealed Bidding Construction (MAR 2019)
A bid may be rejected as nonresponsive if the bid is materially unbalanced as to bid prices. A bid is unbalanced when the bid is based on prices significantly less than cost for some work and significantly overstated for other work.
(End of provision)
Alternate I (MAR 2019). As prescribed in 536.270-5(c), redesignate the basic provision as paragraph (a) and add the following paragraph (b) to the basic provision:
48 C.F.R. §§552.236-76