Section 3052.216-71 - Determination of award feeAs prescribed in (HSAR) 48 CFR 3016.406(e)(1)(i) , insert a clause substantially the same as the following:
Determination of Award Fee (SEP 2012)
(a) The Government shall evaluate contractor performance at the end of each specified evaluation period(s) to determine the amount of award. The contractor agrees that the amount of award and the award fee methodology are unilateral decisions to be made at the sole discretion of the Government.(b) Contractor performance shall be evaluated according to a Performance Evaluation Plan. The contractor shall be periodically informed of the quality of its performance and areas in which improvements are expected.(c) The contractor shall be promptly advised, in writing, of the determination and reasons why the award fee was or was not earned. The contractor may submit a performance self-evaluation for each evaluation period. The amount of award is at the sole discretion of the Government but any self-evaluation received within ___ (insert number) days after the end of the current evaluation period will be given such consideration, as may be deemed appropriate by the Government.(End of clause)
68 FR 67871, Dec. 4, 2003, as amended at 77 FR 50637, Aug. 22, 2012