48 C.F.R. § 243.204-70-6

Current through November 30, 2024
Section 243.204-70-6 - Allowable profit

When the final price of an unpriced change order is negotiated after a substantial portion of the required performance has been completed, the head of the contracting activity shall ensure the profit allowed reflects-

(a) Any reduced cost risk to the contractor for costs incurred during contract performance before negotiation of the final price;
(b) Any reduced cost risk to the contractor for costs expected to be incurred during performance of the remainder of the contract; and
(c) The extent to which costs have been incurred prior to definitization of the unpriced change order (see 215.404-71-3(d)(2)). The risk assessment shall be documented in the price negotiation memorandum.

48 C.F.R. §243.204-70-6

75 FR 48277 , Aug. 10, 2010, as amended at 83 FR 30587 , June 29, 2018
As amended at 83 FR 30587 , 6/29/2018