48 C.F.R. §§ 1850.104-370

Current through September 30, 2024
Section 1850.104-370 - Subcontractor indemnification requests

Subcontractors shall submit requests for indemnification to the prime contractor and through higher tier subcontractor(s), as applicable. If the prime contractor agrees an indemnity clause should be flowed down to the subcontractor, the prime contractor shall forward its written request for subcontractor indemnification to the cognizant contracting officer for approval in accordance with FAR 50.104-3. The prime contractor's request shall provide information responsive to 1850.104-3, FAR 50.104-3, and FAR 50.104-3(b)(1)(i), (ii), (iv), (v), and (vii). The agreed upon definition of the unusually hazardous risk to be incorporated into the subcontract shall be the same as that incorporated in the prime contract.

48 C.F.R. §§1850.104-370