48 C.F.R. §§ 1309.405-1

Current through November 30, 2024
Section 1309.405-1 - Continuation of current contracts
(a) The designee authorized to direct the discontinuance of a contract or subcontract because of a debarment, suspension or proposed debarment is set forth in CAM 1301.70.
(b) A written determination must be issued by the designee authorized in CAM 1301.70 before the following actions can be taken with a contractor that is debarred, suspended or proposed for debarment:
(1) Place any orders exceeding the maximum on an indefinite delivery contract;
(2) Place orders under Federal supply schedule contracts, blanket purchase orders or basic ordering agreements; or
(3) Add new work or exercise options that extend the duration of a current contract or order.

48 C.F.R. §§1309.405-1