48 C.F.R. § 42.1301

Current through September 30, 2024
Section 42.1301 - General

Situations may occur during contract performance that cause the Government to order a suspension of work, or a work stoppage. This subpart provides clauses to meet these situations and a clause for settling contractor claims for unordered Government caused delays that are not otherwise covered in the contract.

48 C.F.R. §42.1301