48 C.F.R. § 25.1102

Current through September 30, 2024
Section 25.1102 - Acquisition of construction

When using funds other than those appropriated under the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-5) (Recovery Act), follow the prescriptions in paragraphs (a) through (d) of this section. Otherwise, follow the prescription in paragraph (e).

(a) Insert the clause at 52.225-9, Buy American-Construction Materials, in solicitations and contracts for construction that is performed in the United States valued at less than$6,708,000.
(1) List in paragraph (b)(2) of the clause all foreign construction material excepted from the requirements of the Buy American statute.
(2) If the head of the agency determines that a higher percentage is appropriate, substitute the higher evaluation percentage in paragraph (b)(3)(i) of the clause.
(3) The contracting officer shall use the clause with its Alternate I to reflect the domestic content threshold that will apply to the entire period of performance, when the senior procurement executive allows for application of an alternate domestic content test for the contract in accordance with 25.201(c). For contracts that the contracting officer estimates will be awarded in calendar year 2022 or 2023, the contracting officer shall insert "60" in paragraph (1)(ii)(A) of the definition of "domestic construction material." For contracts that the contracting officer estimates will be awarded in calendar year 2024, 2025, 2026, 2027, or 2028, the contracting officer shall insert "65". For contracts that the contracting officer estimates will be awarded after calendar year 2028 the contracting officer shall insert "75".
(b)
(1) Insert the provision at 52.225-10, Notice of Buy American Requirement-Construction Materials, in solicitations containing the clause at 52.225-9.
(2) If insufficient time is available to process a determination regarding the inapplicability of the Buy American statute before receipt of offers, use the provision with its Alternate I.
(c) Insert the clause at 52.225-11, Buy American-Construction Materials under Trade Agreements, in solicitations and contracts for construction that is performed in the United States valued at $6,708,000 or more.
(1) List in paragraph (b)(3) of the clause all foreign construction material excepted from the requirements of the Buy American statute, other than designated country construction material.
(2) If the head of the agency determines that a higher percentage is appropriate, substitute the higher evaluation percentage in paragraph (b)(4)(i) of the clause.
(3) For acquisitions valued at $6,708,000 or more, but less than $13,296,489, use the clause with its Alternate I. List in paragraph (b)(3) of the clause all foreign construction material excepted from the requirements of the Buy American statute, unless the excepted foreign construction material is from a designated country other than Bahrain, Mexico, and Oman.
(4) The contracting officer shall use the clause with its Alternate II to reflect the domestic content threshold that will apply to the entire period of performance, when the senior procurement executive allows for application of an alternate domestic content test for the contract in accordance with 25.201(c). For contracts that the contracting officer estimates will be awarded in calendar year 2022 or 2023, the contracting officer shall insert "60" in paragraph (1)(ii)(A) of the definition of "domestic construction material." For contracts that the contracting officer estimates will be awarded in calendar year 2024, 2025, 2026, 2027, or 2028, the contracting officer shall insert "65". For contracts that the contracting officer estimates will be awarded after calendar year 2028 the contracting officer shall insert "75".
(d)
(1) Insert the provision at 52.225-12, Notice of Buy American Requirement-Construction Materials under Trade Agreements, in solicitations containing the clause at 52.225-11.
(2) If insufficient time is available to process a determination regarding the inapplicability of the Buy American statute before receipt of offers, use the provision with its Alternate I.
(3) For acquisitions valued at $6,708,000 or more, but less tha$13,296,489, use the provision with its Alternate II.
(e)
(1) When using funds appropriated under the Recovery Act for construction, use provisions and clauses 52.225-21, 52.225-22, 52.225-23, or 52.225-24 (with appropriate Alternates) in lieu of the provisions and clauses 52.225-9, 52.225-10, 52.225-11, or 52.225-12 (with appropriate Alternates), respectively, that would be applicable as prescribed in paragraphs (a) through (d) of this section if Recovery Act funds were not used.
(2) If these Recovery Act provisions and clauses are only applicable to a project consisting of certain line items in the contract, identify in the schedule the line items to which the provisions and clauses apply.
(3) When using clause 52.225-23, list foreign construction material in paragraph (b)(3) of the clause as follows:
(i)Basic clause. List all foreign construction materials excepted from the Buy American statute or section 1605 of the Recovery Act, other than manufactured construction material from a Recovery Act designated country or unmanufactured construction material from a designated country.
(ii)Alternate I. List in paragraph (b)(3) of the clause all foreign construction material excepted from the Buy American statute or section 1605 of the Recovery Act, other than-
(A) Manufactured construction material from a Recovery Act designated country other than Bahrain, Mexico, or Oman; or
(B) Unmanufactured construction material from a designated country other than Bahrain, Mexico, or Oman.

48 C.F.R. §25.1102

64 FR 72419, Dec. 27, 1999
81 FR 11992, 3/7/2016; 83 FR 3398, 1/24/2018; 85 FR 2618, 1/15/2020; 86 FR 74530, 1/1/2022; 87 FR 12790, 10/25/2022; 89 FR 13963, 2/23/2024

For FEDERAL REGISTER citations affecting § 25.1102, see the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and at www.govinfo.gov.