48 C.F.R. §§ 14.407-1

Current through October 31, 2024
Section 14.407-1 - General

After the opening of bids, contracting officers shall examine all bids for mistakes. In cases of apparent mistakes and in cases where the contracting officer has reason to believe that a mistake may have been made, the contracting officer shall request from the bidder a verification of the bid, calling attention to the suspected mistake. If the bidder alleges a mistake, the matter shall be processed in accordance with this section 14.407 . Such actions shall be taken before award.

48 C.F.R. §§14.407-1

48 FR 42171, Sept. 19, 1983. Redesignated and amended at 60 FR 34738, July 3, 1995