48 C.F.R. §§ 14.402-3

Current through November 30, 2024
Section 14.402-3 - Postponement of openings
(a) A bid opening may be postponed even after the time scheduled for bid opening (but otherwise in accordance with 14.208) and-
(1) The contracting officer has reason to believe that the bids of an important segment of bidders have been delayed in the mails, or in the communications system specified for transmission of bids, for causes beyond their control and without their fault or negligence (e.g., flood, fire, accident, weather conditions, strikes, or Government equipment blackout or malfunction when bids are due); or
(2) Emergency or unanticipated events interrupt normal governmental processes so that the conduct of bid openings as scheduled is impractical.
(b) At the time of a determination to postpone a bid opening under subparagraph (a)(1) above, an announcement of the determination shall be publicly posted. If practical before issuance of a formal amendment of the invitation, the determination shall be otherwise communicated to prospective bidders who are likely to attend the scheduled bid opening.
(c) In the case of paragraph (a)(2) of this section, and when urgent Government requirements preclude amendment of the solicitation as prescribed in 14.208, the time specified for opening of bids will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume. In such cases, the time of actual bid opening shall be deemed to be the time set for bid opening for the purpose of determining "late bids" under 14.304. A note should be made on the abstract of bids or otherwise added to the file explaining the circumstances of the postponement.

48 C.F.R. §§14.402-3

48 FR 42171, Sept. 19, 1983, as amended at 60 FR 34738, July 3, 1995; 61 FR 31619, June 20, 1996