Current through October 31, 2024
Section 1355.56 - Requirements for S/TACWIS and non-S/TACWIS projects during and after the transition period(a) During the transition period a title IV-E agency with a S/TACWIS project may continue to claim title IV-E funding according to the cost allocation methodology approved by ACF for development or the operational cost allocation plan approved by the Department, or both.(b) A S/TACWIS project must meet the submission requirements of § 1355.52(i)(1) during the transition period to qualify for the CCWIS cost allocation methodology described in § 1355.57(a) after the transition period.(c) A title IV-E agency with a S/TACWIS may request approval to initiate a new CCWIS and qualify for the CCWIS cost allocation methodology described in § 1355.57(b) by meeting the submission requirements of § 1355.52(i)(1) .(d) A title IV-E agency that elects not to transition a S/TACWIS project to a CCWIS project must: (1) Notify ACF in an APD or Notice of Intent submitted during the transition period of this election; and(2) Continue to use the S/TACWIS through its life expectancy in accordance with 45 CFR 95.619 .(e) A title IV-E agency that elects not to transition its S/TACWIS project to a CCWIS and fails to meet the requirements of paragraph (d) of this section is subject to funding recoupment described under § 1355.58(d) .(f) A title IV-E agency with a non-S/TACWIS (as defined in § 1355.51 ) that elects to build a CCWIS or transition to a CCWIS must meet the submission requirements of § 1355.52(i)(1) : (1) During the transition period to qualify for a CCWIS cost allocation as described at § 1355.57(a) ; or(2) At any time to request approval to initiate a new CCWIS and qualify for a CCWIS cost allocation as described at § 1355.57(b) . 81 FR 35481 , June 2, 2016