44 C.F.R. § 209.12

Current through November 30, 2024
Section 209.12 - Oversight and results
(a)FEMA oversight. Our Regional Administrators are responsible for overseeing this grant authority and for ensuring that States and subgrantees meet all program requirements. Regional Administrators will review program progress quarterly.
(b)Monitoring and enforcement. We, subgrantees, and States will monitor the properties purchased under this authority and ensure that the properties are maintained in open space use. We and the State may enforce the agreement by taking any measures that we or they deem appropriate.
(c)Program results. The State will review the effectiveness of approved projects after each future flood event in the affected area to monitor whether projects are resulting in expected savings. The State will report to us on program effectiveness after project completion and after each subsequent flood event.

44 C.F.R. § 209.12